  • V-BOR Production -- 6,200 tons in October, representing the first month of output following the acquisition of Searles Valley Minerals.
  • V-BOR Sales -- 2,500 tons in October, reflecting a prioritization of domestic customers while the company established export logistics through the Port of Long Beach.
  • Average Netback -- $767 per ton of V-BOR, driven by the transition of customers from legacy contracts to new take-or-pay and fixed-price agreements.
  • Annualized V-BOR Output -- 82,000 short tons, with management targeting recovery toward 100,000 short tons through facility restarts and well field optimizations.
  • Daily Grid Electricity Savings -- $38,000, expected to be realized by utilizing on-site cogeneration capacity to reduce reliance on the power grid.
  • Net Annual Cost Reduction -- $8 million to $9 million, projected as the outcome of decoupling from external power sources at the Westend plant.
  • Strategic Capital Expenditure -- $500,000 for a new capacitor, intended to stabilize on-site voltage and enable grid independence by summer 2027.
  • Cash Position -- $15.6 million as of Sept. 30, 2026, which excludes additional liquidity accessed following the October acquisition closing.
  • Bridge Facility Draw -- $7 million, received at the time of the asset acquisition closing to support initial operational transitions.
  • Incremental Liquidity -- $3 million remaining under the bridge facility, which management is working to access upon meeting finalized closing conditions.
  • Maintenance Turnaround -- five days in early November, utilized to address equipment reliability and fix process leaks to improve yield.
  • Contracted Sales Volume -- 90% of current V-BOR output, including a minimum of 62,000 tons under multiyear take-or-pay agreements.
  • Working Capital Facility Rate -- SOFR plus 4%, representing the target pricing for a proposed facility supported by offtake agreements.
  • Industrial Salt Deliveries -- 28 trucks per day on average, serving established oil and gas customers in Bakersfield, Calif.
  • Well Field Program -- 205 wells targeted for drilling or workovers, focusing on fresh tincal ore to recover brine grades.
  • Workforce Scale -- approximately 250 employees, following the integration of the Searles Valley Minerals team into the company's operating structure.
  • Natural Gas Procurement Cost -- $6.00 to $6.20 per MMBtu, supporting the economic advantage of self-generated power versus grid electricity.
  • Mineral Tenure -- 9,000 acres at Searles Lake, underpinning the production of borates, sodium sulfate, and industrial salt.
  • Opening Inventory -- 3,000 tons of V-BOR carried into October, positioning the company to fulfill upcoming export shipments to Asia.
  • Monthly Production Target -- 8,300 tons of V-BOR for November, representing the intended run rate as operational efficiencies improve.

Need a quote from a Motley Fool analyst? Email pr@fool.com

RISKS

  • Paul Weibel identified organizational integration challenges, stating that the company "probably saw some resistance" from employees during the initial transition to new benefit systems.
  • Management cited "turbulence" in establishing container logistics and navigating potential labor negotiations at the Port of Long Beach during the first five weeks of ownership.

SUMMARY

5E Advanced (NASDAQ:FEAM) transitioned from a development-stage entity into an operating producer of borates and industrial minerals following the acquisition of Searles Valley Minerals on Oct. 1, 2026. Management reported that the acquisition includes three processing sites, 54 megawatts of cogeneration capacity, and established infrastructure acquired free and clear of legacy liabilities. The company is currently executing a strategy focused on commercial resets, cost optimization through grid independence, and volume recovery across its California assets. Management stated that boron's status as a critical mineral strengthens the company's strategic position as a domestic supplier to energy and defense markets.

  • The company established a logistic network at the Port of Long Beach, enabling container shipments to customers in Malaysia and across Asia.
  • CEO Weibel noted the strength of current demand, stating, "if we could produce 200,000 tons of V-BOR, we could sell the V-BOR."
  • Management plans to restart the Soda Ash Consolidation plant in Jan. to improve brine chemistry and increase total borate output.
  • Initial byproduct testing for lithium and tungsten is underway with third-party partners to explore additional revenue streams from existing brine resources.
  • The company is advancing its advanced materials strategy at Fort Cady, successfully confirming iron boride formation in ferroboron samples during testing at 1,400 degrees Celsius.
  • Management is transitioning customers to documentary letters of credit to support a working capital facility priced at SOFR plus 4%.

INDUSTRY GLOSSARY

  • Cogeneration: The simultaneous production of electricity and useful heat from the same fuel source, used here to power mining operations.
  • Netback: The net revenue received from sales after subtracting all costs associated with bringing the product to market, such as freight and royalties.
  • SAC Plant: Soda Ash Consolidation plant, a facility designed to process brine chemistry to improve the efficiency of borax extraction.
  • Tincal Ore: A natural mineral form of borax used as a primary feedstock for producing borate chemicals.
  • V-BOR: A proprietary term for borax pentahydrate, a critical mineral used in specialized industrial and technological applications.
  • MMBtu: One million British Thermal Units, a standard unit for measuring the energy content of natural gas.

Full Conference Call Transcript

Operator: Good afternoon, and thank you for joining us today for 5E Advanced Materials Fiscal First Quarter 2027 Conference Call and Shareholder Update. During today's call, management will reference the company's quarterly report on Form 10-Q for the quarterly period ended September 30, 2026, which is available in the Investor Relations section of the company's website and on the SEC's website. For a copy of the Form 10-Q, you may also contact PRA Communications at team@pracommunications.com.

As a reminder, remarks made on today's conference call will contain forward-looking statements within the meaning of the safe harbor provisions of the Private Securities Litigation Reform Act of 1995, including statements regarding the acquisition of the Searles Valley Minerals assets and the integration of the acquired operations, the bridge facility and promissory note entered in connection with the acquisition, the transition of customers to take-or-pay and fixed price offtake agreements, the ramp of V-BOR sales volumes and the recovery of V-BOR production towards approximately 100,000 short tons annually; the restart of the SAC plant, the restart of idle boric acid production, the well field development program, reducing reliance on purchase power and the expected cost savings, expected future results, cost, production capacity, market dynamics, capital expenditures, liquidity, cash spending, finance objectives and options, customer demand, purchase order commitments, offtake arrangements, customer qualification activities, commercialization strategy, development plans, engineering and project financing activities, including FEED-related work and the timing and scope of future engineering phases, advancement of supply chain initiatives and products, the potential benefits of our ASX delisting, the potential application of our products across energy, defense and industrial markets, government-based financing opportunities, including EXIM-related diligence, the company's ability to continue operating the small-scale facility and developing the project and the potential development of advanced boron derivative projects, including meta boric acid and ferroboron.

These statements are based on management's current expectations and involve risks and uncertainties that could cause actual results to differ materially and adversely from those projected or discussed. Additionally, information concerning factors that could cause actual results to differ materially and adversely from these forward-looking statements is contained in our disclosures and public filings with the SEC, including our Form 10-Q for the quarter ended September 30, 2026. The company undertakes no obligation to update forward-looking statements, except as required by law.

Today's call may also include a discussion of non-GAAP financial measures as that term is defined in Regulation G, non-GAAP financial measures should not be considered in isolation from or as a substitute for financial information presented in compliance with GAAP. This afternoon's conference call is hosted by 5E Chief Executive Officer, Paul Weibel. Management will first lead off the call by making prepared comments, after which we will open the call for your questions. I will now turn the call over to Paul. Paul?

Paul Weibel: Good afternoon, and thank you for joining us today. The first quarter of fiscal year 2027 marks a defining moment for 5E Advanced Materials. On October 1, one day after quarter end, we closed our asset acquisition of Searles Valley Minerals, acquiring them free and clear of the prior owner's legacy liabilities and historical claims. With that closing, 5E transitioned from a development stage company into an operating revenue-generating producer of borates and industrial minerals. It is worth pausing on what we now own.

Searles Valley includes 3 processing sites, 54 megawatts of on-site cogeneration capacity, the Trona Railway short-line railroad, water utility, approximately 25,000 acres across 3 California counties and mineral tenure across more than 9,000 acres at Searles Lake, operated by an experienced workforce of approximately 250 people. The operation produces V-BOR, which is borax pentahydrate, sodium sulfate and salt, and it includes boric acid production capacity that is currently idled. Together with our Fort Cady project, 5E now holds 2 boron assets in Southern California at a time when boron has been added to the U.S. Department of the Interior's Critical Minerals list. We believe that positions 5E as a strategically important domestic supplier of critical minerals.

Because the acquisition closed just after quarter end, today, I want to focus on our first 5 weeks of ownership and our plan to grow the value of this platform moving forward. That plan is built on the 3 levers we laid out on our acquisition call, price, cost and volume. The focus is now on operational excellence and execution. Each one is already underway, and I will walk you through our progress. First, I'll look at our first month of operations. In October, we produced 6,200 tons of V-BOR, adding to approximately 3,000 tons of V-BOR inventory we carried into the month, and we sold approximately 2,500 tons.

We prioritized our domestic customers in October, while we build out export logistics through the Port of Long Beach. That network is now established, opening container shipments into Asia and the inventory we built in October is positioned to ship into that channel in November. With logistics in place and product on hand, we expect V-BOR sales volumes to ramp as we move through November and into December. Now to the levers starting with price. Through the bankruptcy process, the legacy below-market sales contracts were rejected. That gives us a clean slate on commercial terms, and we have transitioned customers onto new take-or-pay and fixed-price V-BOR offtake agreements.

In our first month, we achieved a V-BOR netback of approximately $767 per ton. Importantly, many of our November V-BOR orders have been prepaid, which speaks to the demand we are seeing for our product. Turning to cost. Power is one of our largest opportunities, and the solution is already on site. We plan to reduce the Westend plant's reliance on purchased power through greater use of our existing 54 megawatts of on-site cogeneration capacity. To enable that, we have engaged a third-party engineering firm to finalize the specifications for a capacitor. We are targeting having that capacitor on order by January with the objective of reducing our reliance on the grid by next summer.

We expect this initiative to require approximately $0.5 million of capital, and it would save approximately $38,000 per day on grid electricity purchases or roughly $14 million gross on an annualized basis, which we expect to reduce operating expenditures by approximately $8 million to $9 million. Beyond power, we are resetting the cost structure through organizational and procurement efficiencies and the elimination of duplicative corporate costs. On to volume. Current V-BOR production is approximately 82,000 short tons on an annualized basis.

Our objective is to recover production towards approximately 100,000 short tons annually through 2 initiatives: the restart of the SAC plant and an engineering-led well field development program, together with incremental byproduct production, including sodium bicarbonate and additional boric acid. We also plan to restart the idle boric acid production at our Trona facility, adding another product line from assets already in place. Reliability underpins that growth. On November 1, we commenced our first planned 5-day maintenance turnaround at the Westend plant. The team completed the work and restarted production on Friday, November 6. This planned downtime allowed us to address equipment reliability and maintenance items that are important to sustaining higher operating rates.

And it is one part of a broader effort to reduce unplanned downtime and strengthen operating performance. During our last update call, we emphasized the restart of the SAC plant, and it remains our most immediate volume catalyst. For those new to the story, SAC stands for Soda Ash Consolidation. It is a small existing facility that was idled as part of the soda ash exit last February, and it can operate independently of the legacy soda ash operation. The SAC plant is designed to capture natural gas emissions into the brine and reduce brine pH, improving brine chemistry and V-BOR output. Bringing it back online is a capital-light way to add volume.

I'm pleased to report that our team has begun the necessary prep work, including maintenance, readiness activities and the steps required for a safe startup. Our target is to have the SAC plant operational in January. Sustained volume growth starts with the resource. So we are also focused on the brine and well field system that underpins production. October brine grade was in line with our modeled expectations, consistent with the assumptions behind our production plan. Today, we kicked off a drilling and workover program addressing 205 wells with new and reworked wells targeting fresh tincal ore with the goal of recovering brine grade towards historical levels.

We also improved heat delivery on the lake by bypassing an underperforming heat exchanger, resulting in more consistent heat. Together with the SAC restart, these initiatives are intended to support stronger brine grades and higher V-BOR production. Beyond borates, our industrial salt and sodium sulfate businesses give us a diversified revenue base serving established industrial customers. Industrial salt operations transitioned seamlessly, averaging approximately 28 trucks per day, delivering industrial salt to key oil and gas customers in Bakersfield, California. In sodium sulfate, we used October to establish the rail and export logistics serving our customers in Mexico.

That work is done, and we are now moving product by rail to the Union Pacific line and onward into Mexico, setting up volumes to build from here. Searles Valley platform also gives us opportunities beyond our current operating plan. We have commenced 2 independent work streams focused on lithium and tungsten, both of which have the potential to become important byproducts that enhance our economics. Reputable third parties have received brine samples and will work to perform initial testing, analytical procedures and process recovery work. These opportunities are at an early stage, but we see them as meaningful optionality on top of our core borates business. We also see longer-term potential in borates expansion and sulfate of potash.

At Fort Cady, we continue to advance our advanced boron material strategy. In August, independent x-ray diffraction analysis confirmed the formation of iron boride in our ferroboron samples. We have since initiated testing at 1,400 degrees Celsius and are planning an approximately 500-gram batch with a third-party metallurgical processing partner as next steps towards producing samples for prospective customers. All of this is being done alongside the integration of the Searles Valley organization into 5E. We held our first employee town hall, and we are working closely with our employees as they transition on to 5E systems, and we have identified critical positions that we intend to fill. I want to personally recognize the Searles Valley team.

Their experience operating this asset is a real advantage for 5E, and I'm grateful for the work they have done during this initial transition. On financing, we ended the quarter with $15.6 million in cash and cash equivalents. And we received $7 million under our bridge facility at closing and are diligently working on the remaining CPs to draw on the remaining $3 million. Customer prepayments on November orders are supporting our working capital and our go-forward plan includes a working capital debt facility supported by our contracted offtake structure, which we are working now to finalize. We remain focused on solutions that optimize 5E's cost of capital.

To sum up, our first 5 weeks have been about establishing a reliable operating platform and a foundation for increasing production, and we have made strong progress. We completed a successful first month, streamlined logistics to drive sales, began resetting our commercial terms, completed a planned maintenance turnaround and advanced the SAC restart that can unlock additional production and sales volumes.

Looking ahead, our milestones are clear: ramping V-BOR sales through November and December, transitioning customers onto new take-or-pay and fixed-price offtake agreements, restarting the SAC plant in January, restarting idle boric acid production in Trona, placing the capacitor order by January, reducing our reliance on the grid by next summer and recovering V-BOR production towards approximately 100,000 short tons annually. Our focus remains on safely increasing volumes, improving reliability and cost and strengthening commercial execution. We believe the combination of Searles Valley's operating platform today and Fort Cady's long-term resource opportunity positions 5E for its next phase of growth, and we are excited about the road ahead. With that, we're ready to open up the call for questions.

Operator: [Operator Instructions] Your first question is coming from Dmitry Silversteyn from Water Tower Research.

Dmitry Silversteyn: I just wanted to clarify your numbers on the sale of V-BOR -- production of V-BOR. You talked about 6,200 tons that you produced in November, and you had, I think you said 1,300 tons in inventory. So that's about 7,500 tons and you sold 2,500. So when you talk about ramp-up in November versus October, are you looking at kind of selling the rest of that? I'm just trying to understand what the run rate in November and December is going to be given the 2,500 ton sale in October.

Paul Weibel: Yes. Inventory was a little over 3,000 tons when we...

Dmitry Silversteyn: 3,000 tons.

Paul Weibel: Yes, 3,000 tons. No, targeted production is about 8,200 tons. So I think we got in, met with the team and I think kind of came out of the gates and then planned for the kind of first downtime. We had a power outage that knocked us down for a day in that month, and then we kind of build back up the rates. So I think the goal and the target right now for November is approximately 8,300 tons. And I think you did 6,200 on month 1. I didn't quite know what it would look like once we came in, Pleasantly surprised to see about 3,000 tons in inventory.

And I think targeting on kind of hitting those rates.

Dmitry Silversteyn: Got it. Okay. And then just to clarify on the cost savings from the switching off the power grid and going to your cogeneration plant. You talked about $40 million in gross savings and then you talked about $8 million to $9 million in savings. Is that -- are both of those annual numbers?

Paul Weibel: Yes. No. So what will happen here is -- and it's good to get into those details. So approximately what we're buying from the grid at Westend is about $38,000 a day, right? So $38,000 times 365 gives you kind of your gross number that we're paying to SoCal Edison. The lines and the infrastructure are set up to fully decouple from the grid, but we get a voltage sag. And so we require a capacitor to ultimately stand that up. And so once we do that, we'll -- there's going to be an incremental MMBtu of natural gas we'll procure.

But all day long at $6 to $6.20 all-in MMBtu, that makes sense to buy that every day of the week. So the net savings, like the OpEx kind of reduction on a net basis is targeted to be $8 million to $9 million.

Dmitry Silversteyn: Understood. So that's -- okay. So that's the cost savings minus the purchase of gas and the cost of operating the plant.

Paul Weibel: Yes.

Dmitry Silversteyn: Got it. Okay. And then in your 5-day outage -- maintenance outage, you talked about everything kind of going according to plan. Any -- maybe not surprises, but anything you've learned as you've worked through the maintenance of that equipment that affected you one way or the other about your plans?

Paul Weibel: No. Like it's a good question. I think there was a handful of safety fixes and get-rights that needed to occur right away. There was a tank that hadn't been cleaned out and emptied in about 10 years, hadn't seen the bottom of the tank. That was effectively drained and then cleaned out and the agitators were -- rigs were kind of maintained or working in good order. And there's a lot of leaks -- and we can quantify based on our concentrations, where we are in the process and the solution. A leak of 10 gallons a minute, if it's got 2% to 5%, whatever borax in it, that's dollars that are going on the ground.

So a lot of the focus was on that and just fixing a lot of the leaks and starting to build in redundancies that really focus on uptime reliability. So I think it's -- I think the punchline and takeaway was, listen, it needs TLC. That was a big focus out of the gate and kind of did that. And I think we -- it was very planned. So that's why I think we started November 1st or 2nd and came right out of it on the 5th.

Dmitry Silversteyn: Excellent. So it sounds like you're getting your hands around in at least the first 5 weeks around this asset and really starting to understand what levers you need to pull. So that's good to see.

Operator: Your next question is coming from Adam Kelsey from Titan Partners.

Adam Kelsey: Paul, just one point of clarity. How much of the current V-BOR output falls under the new take-or-pay contracts? And how quickly do you expect to address any remaining legacy contracts?

Paul Weibel: We have -- you're probably about 90% all in. The take-or-pays have -- when I look at them, there's minimum 62,000 tons under contract, but then they also have maximums. And I think not required to sell the maximum, but they're really great customers, and we want to service them. And I think there's a small percentage that are kind of spot or kind of smaller 1,000 tons a year to 1,500 tons that they're kind of contracts via a simple 1-page doc, but there's 5 customers right now, and that accounts for the majority of our volumes.

Adam Kelsey: And with respect to the customer prepayments in November, is that going to be a regular standard course of business? Or is this just kind of a onetime exception?

Paul Weibel: No. I think it's funny. The demand is very real. So I think some of the customers have figured out that, okay, happy to prepay if I can go higher in line and get my allocation. But all these offtakes come with about 60 days of documentary letters of credit. And so the goal here is to actually transition them from prepays. We're working with a financial institution that will basically stand up a working capital facility at basically SOFR plus 4%. And so all of these customers have been vetted. And once we're in the process of transitioning them over to the documentary LCs, which give us the working capital, that's for probably 3 out of the 5.

One of the other offtakes, actually, the customer negotiated, they're prepaying for the first 6 months. So you kind of -- you have a bit of a mix, and it is quite helpful on the working capital draw.

Adam Kelsey: Got it. And obviously, it's still early days with about 6 weeks since you acquired the asset. I would appreciate, though, to see any early learnings or anything that surprised you from the last 6 weeks?

Paul Weibel: No, great question. Listen, I think I don't -- I want to give the team a lot of credit for opening up those supply chains for all the exports. All the -- the majority of the sodium sulfate is going down into Mexico and 4 out of our 5 contracted by customers are all based out of Asia. And so you're dealing with -- they've been navigating. -- there's a new union contract getting negotiated in Long Beach that have kind of caused -- it's been moving, but like everyone is paying attention to that.

And I think there's inspections that have been required and just bills of lading needs to match and we stood up a new entity, the actual contracting entity was stood up probably maybe September 15th, 5E SVM was the buyer, but below 5E SVM are 3 stand-alone entities. And so all that -- there's a lot that goes into the basic execution of taking product up in Trona, packaging it, getting that onto a truck with a container, making sure that gets them into the right loading dock in Long Beach that gets on the right container destined for Malaysia, getting to then Malaysia and then to customers.

So that was probably -- we knew it would be not so straightforward. And maybe a little bit of turbulence there, but I think a lot of lessons learned, and we now are -- we're stood up and we're going. I think we're 15 trucks a day picking up all that product that's staged in the warehouse and it's moving.

Adam Kelsey: Great. Final question for me, and I'll jump back in the queue. You mentioned that there are some positions that you need to fill. I just want to clarify, are these existing legacy positions? Or are these newly created positions? And is there a theme amongst what you need to address?

Paul Weibel: Yes. I think there was -- when we came in, there was still employees that were kind of working through the wind down of some of the soda ash contracts. And so then there was some employees based at Overland Park that didn't get offers. And I think we didn't want to mess too much with org charts. And there was some kind of -- there was definitely a population of open roles that were on the org chart, but we sort of just said, let's get in, let's assess, and then go from there. And so I think HR has a role that we've posted, there's a mechanic. Utilities has 3 operators that they need to fill.

So we're gearing up to start posting those roles. And for the utilities team, they're critical roles because the stack plant literally sits right next to our utilities control room, and they have capacity to kind of manage the SAC plant as well. So we want to get those roles kind of filled to get people trained up. And it's -- we're not talking about a bunch of roles, but there's probably 5, 6, 7 roles that are going to get filled here in the next kind of 4 to 6 weeks.

And to the extent that SAC comes online here in January, as we expect, we have a 30-day drill program going into fresh tincal ore, if that can drive a higher brine grade, that drives more primary borax production, and that brings on Trona and restarting boric acid and maximizing Westend sooner than later. So I think we kind of -- my model is pretty conservative, but like we'll kind of see how it goes.

Operator: Your next question is coming from Heiko Ihle from H.C. Wainwright.

Heiko Ihle: Paul, I somehow got into the queue a little later than I thought, so bear with me here. But just building on the last question a little bit. Can you walk us through the mood at site as you're seeing it right now? How are customers -- or rather employees taking the transition? I assume everyone is getting along fine. It sounds like you're hiring additional staff, at least to a certain extent. Maybe just walk us through what you're seeing in the tranches and maybe give a bit of color beyond what we saw in the press release.

Paul Weibel: Yes. Heiko, glad you're here. Appreciate the question, too. Listen, the culture and that integration is probably one of the more taller orders in this acquisition. I think in the first kind of -- it took about 1.5 weeks or so, and then I've been up there twice a week with the team and just really getting to know our people. We had a town hall. We'll actually -- we're scheduling our next town hall. We'll do it after every quarter. A lot of questions. It was definitely a bumpy -- for a lot of the employees, we went from 25 people to 250 people as of October 1, approximately. And we had 5E benefits. Now we're a smaller company.

So our benefits weren't as good as what they previously had. But we were able to at least offer benefits and bolt everyone on. Now we'll go back to market here in the new year. And so I think out of the gate, there was definitely received skepticism as I think would be kind of normal, but I think there's a rational reason on why we've done something or made a decision. And similar to how I need to answer to shareholders, the leadership team here at 5E needs to answer to our employees. And there's not just an arbitrary decision.

And I think what we've seen is a positive inflection over culture as we just talk to people and get to know them. And so it's really that boots on the ground implementation and letting people know and explaining to them why we've done what we've done. And so candidly, out of the gate, probably saw some resistance. But I think once we've started to talk to people and really explain them and I've met with -- I've been able to make turnover shifts at 6:00 a.m. or 6:00 p.m. and I've gotten to talk to Westend teams and utilities, but not every team within the organization, there's 4 shifts.

So I'm trying to catch people at turnovers and just talk through them. And there's -- we're having leadership meetings on a weekly basis that basically can ensure that everyone is over the details of the organization because it really is an integrated facility and platform where power drives heat to the lake, lake drives brine and borates to Westend, Westend puts out tons, and they need power and good brine to run. So it's very much an integrated organization and just making sure people are informed and there's a rhyme and a reason for decision has been critical.

Heiko Ihle: Fair enough. Walk me through -- just as a follow-up, I guess, walk me through your conversations with clients. I mean, obviously, the economy and the world geopolitically has changed quite a bit in the last, call it, 9 months, 6 months, whatever. Capital markets are much more volatile than they were. I assume getting product from geopolitically safe jurisdictions is what they want. I assume a bit of a conversation in regards to paying a premium for that is actually going over reasonably well. Same thing, what are you seeing in your actual conversations that maybe you could comment here on a public call?

Paul Weibel: Yes, great question. I think the buying from a U.S. entity domestic is important. We have one of the best jurisdictions in the world. I think customers appreciate that third supplier in an oligopoly market, which is what we really are able to offer. And I'll be honest, like we've -- our commercial team has -- I've seen it through the website inbound as well as our commercial team. Mark's been in the borate business for 25-plus years. And, man, if we could produce 200,000 tons of V-BOR, we could sell the V-BOR. It is a very tight market.

I think USGS got it right in November last year by adding boron as a critical mineral, and it is truly a supply and demand story. And I think the belief is -- I think customers see it. A lot of these customers, Mark was able to be in Asia like the first week out of the acquisition. That definitely helped lay the groundwork for the prepays. And I think customers are quite uncomfortable being that this is an oligopoly structure, and they do like that it's an American-owned company that they're able to buy from.

Operator: [Operator Instructions] Thank you. That concludes our Q&A session. I will now hand the conference back to Chief Executive Officer, Paul Weibel, for closing remarks. Please go ahead.

Paul Weibel: Thank you to everyone for joining the call today. We look forward to keeping you updated as we work hard to achieve the next phase of milestones. Have a great day.

Operator: Thank you. Everyone, this concludes today's event. You may disconnect at this time, and have a wonderful day. Thank you for your participation.

Should you buy stock in 5e Advanced Materials right now?

Before you buy stock in 5e Advanced Materials, consider this:

The Motley Fool Stock Advisor analyst team just identified what they believe are the 10 best stocks for investors to buy now… and 5e Advanced Materials wasn’t one of them. The 10 stocks that made the cut could produce monster returns in the coming years.

Consider when Netflix made this list on December 17, 2004... if you invested $1,000 at the time of our recommendation, you’d have $321,850!* Or when Nvidia made this list on April 15, 2005... if you invested $1,000 at the time of our recommendation, you’d have $955,232!*

Now, it’s worth noting Stock Advisor’s total average return is 793% — a market-crushing outperformance compared to 203% for the S&P 500. Don't miss the latest top 10 list, available with Stock Advisor, and join an investing community built by individual investors for individual investors.

See the 10 stocks »

*Stock Advisor returns as of November 18, 2026.

This article is a transcript of this conference call produced for The Motley Fool. While we strive for our Foolish Best, there may be errors, omissions, or inaccuracies in this transcript. Parts of this article were created using Large Language Models (LLMs) based on The Motley Fool's insights and investing approach. It has been reviewed by our AI quality control systems. Since LLMs cannot (currently) own stocks, it has no positions in any of the stocks mentioned. As with all our articles, The Motley Fool does not assume any responsibility for your use of this content, and we strongly encourage you to do your own research, including listening to the call yourself and reading the company's SEC filings. Please see our Terms and Conditions for additional details, including our Obligatory Capitalized Disclaimers of Liability.

The Motley Fool has no position in any of the stocks mentioned. The Motley Fool has a disclosure policy.

Disclaimer: For information purposes only. Past performance is not indicative of future results.
placeholder
Anthropic is six times oversubscribed at $1.4 trillion while Nvidia is down 32% — the AI trade has two pricesAnthropic lists on Nasdaq as ANT on Thursday at $70 ~ $78 a share, raising up to $64.4 billion at a target valuation near $1.4 trillion, and the book is reportedly six times covered. In the same six weeks, Nvidia has fallen 32% and the QQQ is 10.9% below its October peak. Private capital and public markets are marking the same AI complex at two very different prices. This piece separates the two books: what the S-1 shows, who is anchoring the $26 billion private placement, and what Thursday's debut would have to do to change the public tape.
Author  Irene Q.
Nov 16, Mon
Anthropic lists on Nasdaq as ANT on Thursday at $70 ~ $78 a share, raising up to $64.4 billion at a target valuation near $1.4 trillion, and the book is reportedly six times covered. In the same six weeks, Nvidia has fallen 32% and the QQQ is 10.9% below its October peak. Private capital and public markets are marking the same AI complex at two very different prices. This piece separates the two books: what the S-1 shows, who is anchoring the $26 billion private placement, and what Thursday's debut would have to do to change the public tape.
placeholder
Gold Price Analysis Today | Forex Gold Analysis | XAU/USD Analysis - November 16, 2026Get the latest gold price analysis, forex gold insights, and XAU/USD analysis for November 16, 2026. Read on for the details.
Author  Mitrade
Nov 16, Mon
Get the latest gold price analysis, forex gold insights, and XAU/USD analysis for November 16, 2026. Read on for the details.
placeholder
Weekly Report: DXY 103.41, 10-year 5.15%, AUD carry 3bp — three FX regimes flipped in one weekThe dollar index rose 1.09% to 103.41, a 19-month high, while the US 10-year closed at 5.154% and the Australia-US two-year spread collapsed to about 3 basis points from 36. EURUSD fell 1.59% to 1.1024, USDJPY rose 1.51% to 159.78 and AUDUSD fell 1.79% to 0.6764, a 10-month low. Three FX regimes — the broad dollar, the US rate level and the Australian carry premium — flipped in the same week. This report marks the thresholds, ranks which one can flip back first, and lists the week's calendar.
Author  Irene Q.
Nov 16, Mon
The dollar index rose 1.09% to 103.41, a 19-month high, while the US 10-year closed at 5.154% and the Australia-US two-year spread collapsed to about 3 basis points from 36. EURUSD fell 1.59% to 1.1024, USDJPY rose 1.51% to 159.78 and AUDUSD fell 1.79% to 0.6764, a 10-month low. Three FX regimes — the broad dollar, the US rate level and the Australian carry premium — flipped in the same week. This report marks the thresholds, ranks which one can flip back first, and lists the week's calendar.
placeholder
Gold Price Analysis Today | Forex Gold Analysis | XAU/USD Analysis - November 17, 2026Get the latest gold price analysis, forex gold insights, and XAU/USD analysis for November 17, 2026. Read on for the details.
Author  Mitrade
Yesterday 05: 40
Get the latest gold price analysis, forex gold insights, and XAU/USD analysis for November 17, 2026. Read on for the details.
placeholder
Gold Price Analysis Today | Forex Gold Analysis | XAU/USD Analysis - November 18, 2026Get the latest gold price analysis, forex gold insights, and XAU/USD analysis for November 18, 2026. Read on for the details.
Author  Mitrade
12 hours ago
Get the latest gold price analysis, forex gold insights, and XAU/USD analysis for November 18, 2026. Read on for the details.
goTop
quote