ConocoPhillips Q3 2025 Earnings Transcript

Source The Motley Fool

Image source: The Motley Fool.

DATE

Thursday, November 6, 2025 at 12 p.m. ET

CALL PARTICIPANTS

Chairman and Chief Executive Officer — Ryan M. Lance

Executive Vice President, Finance and Commercial and Chief Financial Officer — Andy O'Brien

Executive Vice President, Global Operations — Nick Olds

Senior Vice President, North America — Kirk Johnson

Need a quote from a Motley Fool analyst? Email pr@fool.com.

RISKS

Willow Project Capital Escalation — The total projected capital for the Willow project increased to $8.5 billion–$9 billion, with management citing "higher than expected general inflation and localized North Slope cost escalation."

Willow Project F&D Cost Increase — CEO Lance said, "the estimate increase does impact the cost supply of this individual project," with finding and development (F&D) cost per BOE up by $2–$2.50.

TAKEAWAYS

Production Volume -- 2,399,000 barrels of oil equivalent per day, which exceeded the high end of production guidance.

Adjusted Earnings -- $1.61 per share adjusted (non-GAAP) for the quarter.

Cash from Operations (CFO) -- $5.4 billion generated in the quarter.

Capital Expenditures -- $2.9 billion, declining sequentially as major project capex peaks subside.

Shareholder Returns -- $2.2 billion returned in the quarter, comprising $1.3 billion in share repurchases and $1 billion in dividends.

Base Dividend -- Increased by 8%, with management emphasizing its "goal to deliver top quartile dividend growth relative to the S&P 500."

Cash Balances -- $6.6 billion in cash and short-term investments, plus $1.1 billion in long-term liquid investments.

Full-Year 2025 Production Guidance -- Raised to 2,375,000 barrels of oil equivalent per day, even after including the Anadarko asset sale closed October 1.

2025 Operating Cost Guidance -- Reduced to $10.6 billion, down from $10.8 billion midpoint prior and an initial $11 billion at year start.

Asset Sales -- $3 billion total announced toward the $5 billion target; $600 million closed and received through the quarter, with $1.5 billion set to close in Q4.

Willow Project Progress -- Project capital estimate raised to $8.5 billion–$9 billion, with 50% completion achieved as of the update and first oil targeted for early 2029.

Willow Project CapEx Trajectory -- 2025 capital just north of $2 billion, declining to approximately $1.7 billion per year in 2026–2028, and settling at $500 million annual sustaining capital post–first oil.

Willow Free Cash Flow Contribution -- $4 billion free cash flow inflection expected in 2029 upon first oil.

LNG Project Capital -- Three equity LNG projects' capital estimate reduced from $4 billion to $3.4 billion due to a $600 million infrastructure credit; 80% of this capex now spent, with $800 million remaining.

LNG Offtake Commitments -- Portfolio now at 10 million tonnes per annum (mtpa) offtake, including recent agreements for 4 mtpa (Port Arthur Phase 2) and 1 mtpa (Rio Grande LNG), representing the lower end of the 10–15 mtpa goal.

2026 CapEx and OpEx Framework -- Preliminary 2026 capex framework at ~$12 billion, about $5 billion below 2025 guidance midpoint; 2026 operating costs expected at $10.2 billion, down $400 million from 2025 and $1 billion from pro forma 2024 with Marathon Oil.

2026 Underlying Production Outlook -- Guidance is for flat to up 2% production growth, citing macroeconomic volatility.

Free Cash Flow Growth -- $7 billion free cash flow inflection expected by 2029 from four major projects plus $1 billion in cost reductions and margin enhancements; $1 billion per year expected 2026–2028, followed by $4 billion in 2029.

Marathon Oil Synergies -- 75% of targeted synergies have been realized, with full integration expected by year end and ongoing cost benefits into 2026.

Oil Mix Guidance -- Company-wide oil mix for 2026 guided to 53%; Lower 48 oil mix projected at 50%.

Dividend Breakeven -- Ryan Lance said, "our breakeven is coming down and it's coming down pretty substantially," with capital breakeven expected to reach the low thirties WTI by the end.

SUMMARY

During the call, ConocoPhillips (NYSE:COP) highlighted both a notable upgrade and several operational shifts that have consequences for investor assessment. Willow project capital projections increased sharply, attributed mainly to rising inflation and localized cost escalation, yet the timeline to first oil remains unchanged at early 2029. Liquefied natural gas (LNG) capital efficiency improved as project capex was reduced and commercial offtake volumes approached the lower bound of management's stated target. Management provided precise 2026 guidance, signaling a meaningful step down in both capital and operating expense, with modest production growth expected in a volatile macro environment.

Sustained free cash flow inflection is a central theme, with management reiterating a $7 billion uplift by 2029 split across major projects and cost initiatives.

Shareholder return discipline was underscored by an 8% dividend increase, complemented by continued buybacks funded from a strong cash position and reduced breakeven targets.

Operational flexibility was emphasized, including the ability to rapidly scale investment or pare back capital deployment as macro conditions warrant.

The Lower 48 region has transitioned to a steady-state capital and rig program, benefiting from realized Marathon Oil synergies and ongoing efficiency improvements.

Management highlighted progress towards regulatory streamlining in Alaska, which may benefit further resource opportunities tied to Willow in future periods.

INDUSTRY GLOSSARY

BOE: Barrels of oil equivalent, a standard unit measuring oil and gas output in energy-equivalent terms.

Willow Project: Large-scale oil development project in Alaska's North Slope with significant capital and anticipated cash flow impact for ConocoPhillips.

mtpa: Million tonnes per annum, common LNG volume metric used in long-term offtake and capacity agreements.

FID: Final Investment Decision, the formal commitment to move forward with material project spending and execution.

OpEx: Operating expenditures, referring to ongoing operating costs excluding capital investments.

Delaware: Refers to the Delaware Basin, a major oil and gas producing region and part of the Lower 48 operations for ConocoPhillips.

Finding and Development (F&D) Cost: All-in cost metric for adding reserves through both exploration and development activities, typically shown per BOE.

Full Conference Call Transcript

Ryan Lance: Thanks, Guy, and thank you to everyone for joining our third quarter 2025 earnings conference call. We have a lot to cover today, including our third quarter results, improved 2025 outlook, strategic updates, and our preliminary 2026 guidance. Now starting with our third quarter results, this was another very strong execution quarter. We again exceeded the top end of our production guidance, demonstrating the power of our diversified portfolio, with both capital spending and operating costs declining quarter on quarter. On the back of this strong performance, we raised our full-year production guidance and we have reduced our adjusted operating cost guidance for the second time this year.

In fact, we have improved all our major guidance drivers since the 2025 CapEx, operating costs, and production, further demonstrating the strength of our team's execution. On return of capital, we raised our base dividend by 8%, consistent with our goal to deliver top quartile dividend growth relative to the S&P 500. This type of dividend growth is sustainable, given the strength of our outlook and expectation for our free cash flow breakeven to decline into the low thirties WTI by the end of the decade. Year to date, we've returned about 45% of our CFO to shareholders, in line with our full-year guidance and our longer-term track record.

Turning to our strategic update, at the Willow project in Alaska, after completing our largest winter construction season and conducting a comprehensive project review, we've increased our project capital estimate to $8.5 billion to $9 billion. This change is primarily attributable to higher than expected general inflation and localized North Slope cost escalation. Despite cost pressures, we have maintained the project schedule and made excellent progress on scope execution, narrowing first oil to early 2029. We also continue to advance our global LNG projects, another key driver of our expected free cash flow inflection. We have reduced total LNG project capital by $600 million.

Our three equity projects, NFE and NFS in Qatar, and phase one at Port Arthur LNG, are on track and have been substantially derisked. Capital spending is now about 80% complete with our first start-up expected next year at NFE. Looking ahead to 2026, recognizing it's early, the macro remains volatile, and that our portfolio is highly flexible, our preliminary guidance for both CapEx and OpEx is to be improved significantly, down about $1 billion on a combined basis from this year. And in fact, relative to our pro forma 2024, they are down about $3 billion. Underlying production should be flat to up next year, a reasonable starting point given the current macro environment.

Looking beyond just the near term, ConocoPhillips continues to operate a compelling value proposition to the market, one that is differentiated relative to our sector and to the broader S&P 500. We believe we have the highest quality asset base in our peer space. Our global portfolio is deep, durable, and diverse, with the most advantaged US inventory position in the sector. We are uniquely investing in our portfolio and driving significant efficiencies throughout the organization to deliver improving returns on and of capital, and a leading multiyear free cash flow growth profile.

Consistent with our guidance last quarter, we continue to expect the four major projects we are progressing along with our recently announced cost reduction and margin enhancement efforts to drive a $7 billion free cash flow inflection by 2029, potentially doubling the consensus expectation for key free cash flow this year. That free cash flow inflection is now underway. We expect to realize about $1 billion annually through 2026 through 2028 before an additional $4 billion in 2029 once Willow comes online. That's a growth trajectory that's unmatched in our sector. So bottom line, we're performing well, we're delivering on our plan, and we're well positioned for 2026 and beyond.

Now with that, let me turn the call over to Andy to cover our third quarter performance, major project updates, and 2026 guidance in more detail.

Andy O'Brien: Thanks, Ryan. Starting with our third quarter performance, as Ryan mentioned, we had another quarter of strong execution across the portfolio. We produced 2,399,000 barrels of oil equivalent per day, once again exceeding our high end of our production guidance. Regarding third quarter financials, we generated $1.61 per share in adjusted earnings and $5.4 billion of CFO. Capital expenditures were $2.9 billion, down quarter on quarter as we passed the peak of our major project capital investment cycle. We returned over $2.2 billion to our shareholders, including $1.3 billion in buybacks and $1 billion in ordinary dividends.

Through the third quarter, we've now returned $7 billion to our shareholders or about 45% of our CFO, consistent with our full-year guidance and our long-term track record. We ended the quarter with cash and short-term investments of $6.6 billion plus $1.1 billion in long-term liquid investments. Turning to our outlook for 2025, we've raised our full-year production guidance to 2,375,000 barrels of oil equivalent per day, up 15,000 from our prior guidance midpoint. This is even after considering Anadarko's sale of 40,000 barrels a day of oil equivalent which closed on October 1.

We're reducing our operating cost guidance to $10.6 billion, down from the prior guidance midpoint of $10.8 billion and our initial guidance at the beginning of the year of $11 billion. We are also making great progress on our asset sales program, with another $500 million on top of what we announced last quarter. That takes us up to over $3 billion of asset sales out of our $5 billion target. Of this amount, $600 million was closed and the cash was received through the third quarter and we have another $1.5 billion that will have closed in the fourth quarter. That includes the remainder of the Anadarko disposition proceeds as well as additional noncore Lower 48 assets.

Turning now to our strategic updates. At Willow, we have updated our total project capital estimate to $8.5 billion to $9 billion. After successfully completing peak winter season, we undertook a detailed bottom-up reforecast of the project. And as a result, have increased our cost estimate. The increase is primarily due to higher general labor and equipment inflation and increased inflation on North Slope construction. Scope execution has remained strong, we're nearing 50% project completion. This has allowed us to narrow our estimate of initial production to early 2029. Importantly, we can now level load the pace of our future work. More specifically, 2025 Willow project capital is forecast to be just north of $2 billion.

We plan to reduce capital to around $1.7 billion a year from 2026 through 2028. After achieving First Oil, ongoing development capital will decline to about $500 million a year for several years. We continue to expect Willow to deliver $4 billion of free cash flow inflection in 2029, consistent with our prior commentary. Turning to our three LNG projects, NFE and NFS in Qatar, and Port Arthur LNG phase one, we are reducing our total project capital estimate from $4 billion to $3.4 billion. This reduction is due to a $600 million credit from put up of phase two. The credit is for shared infrastructure costs previously incurred by Phase one equity holders.

As a reminder, we only have equity in Phase one, not Phase two. With this credit, we're approximately 80% complete with our total project capital for these three LNG projects. Approximately $800 million of project capital remains, averaging just north of $250 million of spend annually with a declining trend from 2026 to 2028. All projects remain on track. We continue to expect first LNG from NFE in 2026, Port Arthur in '27, and NFS after that. We're also making considerable progress in advancing our commercial LNG strategy, which will further strengthen our long-term free cash flow generation capacity. As a reminder, our strategy is to connect low-cost supply North American natural gas to higher value international markets.

We are leveraging our decades of LNG experience and our global scale to advance our strategy, which nicely complements our more than two Bcf a day or 15 mtpa equivalent of Henry HubLink U.S. Natural gas production. We have fully placed the first five mtpa from Port Arthur phase one with combined regas and sales agreements into Europe and Asia. In terms of offtake, we recently agreed to take four mtpa from Port Arthur Phase two and one mtpa from Rio Grande LNG, bringing our total offtake portfolio to about 10 mtpa, the lower end of our stated 10 to 15 mtpa ambition. Now turning to our outlook for 2026.

We are providing a high-level framework assuming about a $60 a barrel WTI price environment. First, we continue to expect a significant reduction to our capital spend next year, about $5 billion lower than the midpoint of our 2025 guidance. So in round numbers, that's about $12 billion for 2026. The year-on-year decline is driven by a reduction in our major project spend including Willow, and the steady state activity we achieved on the Lower 48 Marathon Oil assets earlier this year. In addition to lowering our capital spend, in 2026, we also expect to lower our operating costs. This is largely due to the $1 billion of cost reduction and margin enhancement efforts we disclosed last quarter.

We expect our cost in 2026 to be approximately $10.2 billion, down $400 million from our current year guidance and down $1 billion from our pro forma 2024 operating costs including Marathon Oil. Turning to our production, we expect to deliver flat to 2% underlying growth in 2026, a reasonable planning assumption considering the ongoing macro volatility. Additional guidance can be found in our earnings material including our oil mix and our equity affiliate distributions. Now addressing our multiyear outlook, there are a few important points I'd like to make. First, the free cash flow inflection guidance we previously provided remains unchanged.

We expect our four in-progress major projects and our $1 billion cost reduction and margin enhancement efforts to deliver $7 billion of free cash flow inflection by 2029. In terms of the timing of that $7 billion, we expect to realize about $1 billion of improvement each year from 2026 through 2028, amounting to $3 billion of free cash flow improvement by 2028. The remaining $4 billion will come in 2029 once Willow starts up. Bottom line, using 2025 consensus as a baseline, this translates to a double-digit free cash flow growth CAGR through 2028, before another material step up in 2029 which will approximately double our 2025 free cash flow.

So to wrap up, we continue to execute well operationally, financially, and across our strategic initiatives. We are well positioned for a strong finish to the year and a good start to 2026. And we continue to find ways to enhance our differentiated long-term investment thesis. That concludes our prepared remarks. I'll now turn it over to the operator to start the Q&A.

Liz: Thank you. We will now begin the question and answer session. In the interest of time, we ask that you limit yourself to one question. If you have a question, please press 11 on your touch-tone phone. If you wish to be removed from the queue, please press 11 again. If you're using a speaker phone, you may need to pick up the handset first before pressing the numbers. Once again, if you have a question, please press 11 on your touch-tone phone. Our first question comes from Neil Mehta from Goldman Sachs. Your line is now open.

Neil Mehta: Yeah. Good morning, Ryan, Andy, team. I appreciate the time here, and I want to unpack Willow a bit because while there was a lot of good stuff in terms of execution in the quarter, the Willow update, obviously, was a little disappointing. So one, your perspective on the bridging from the $7 to $7.5 to $8.5 to $9 billion, do you feel, Ryan, that we've got a good handle around the project at this point because the history of major capital projects sometimes is, you know, there are multiple legs of announcements around overruns. And on the bright side, it seems like while there's a cost overrun here, the timing's really intact.

So just unpacking slide four would be great.

Ryan Lance: Yeah. Thank you, Neil. Appreciate the question and, certainly, appreciate the project for the company. And I know giving some clarity on where we've been, where we're at today, and what that future looks like is important to provide that insight and the clarity. So I've asked Kirk to unpack this a little bit using your words, Neil, and spend a little bit of time to make sure you all understand sort of where we're at today and where we're going in the future. So let me ask Kirk to do that and provide a lot more clarity to that.

Kirk Johnson: Yeah. Morning, Neil. Certainly, as you heard in our prepared remarks here this morning, Ryan and from Andy, we are increasing our guide on total project capital for the Willow project to a range of $8.5 billion to $9 billion. And I'll start by recognizing the strong execution that we've been achieving through our project team. Certainly, as you've heard from me before, we're hitting the key milestones that we premised in our project plan that, of course, we laid out at FID back in 2023. And so and this past quarter, we chose to perform a pretty rigorous bottoms-up comprehensive project review, and we were looking at scope schedule, of course, total project cost.

And we were doing that in recognition that we knew we were coming in on about 50% completion. Expect to see that as we move into this next winter season. And it's common practice for us to take on a pretty rigorous, again, bottoms-up at this place and projects of this nature and of this size. And coming out of that exercise, we were able to provide two new guides. On the project, not just capital, but also on schedule. So starting with the first, the new guide on capital is a confirmation, really largely of one driver. That's what we've realized higher inflation post FID in 2023.

So addressing that maybe a little bit more detail here, total inflation is roughly 80% of the increase on our new capital guide, and I'll start with general inflation, which has been modestly higher across a few key categories that we've seen on the projects. General labor, materials, and then engineering equipment as well. And all of that makes up over half, and in fact, about 60% of our total project spend. So seeing that higher inflation is really culminating largely in what you're seeing in this new capital guide. As you can imagine, just a few percent higher, we originally expected just a couple percent of routine standard inflation.

Across the period of the project, but just a couple percent higher in inflation rates across the five-year duration on a project is driving this 15% increase. Against what was our original expectations at FID. Expecting lower inflation. And then a bit more unique to this project, we've also incurred some localized escalation. Particularly in our Alaskan North Slope specific markets. And it's really been driven by the fact that we've incurred more overlap of the peak construction seasons between our project and other projects ongoing in Alaska than we had originally expected, and that's resulting in roughly a 2x increase in the regional activity there in the state. That stressed the local markets. Think labor.

Logistics, such as trucking marine, and then even the availability of camps for our construction work there on this road. We're often asked about tariffs. We have seen some impacts on tariffs, but albeit it's really been low single-digit percentages. As a total of the increase we're seeing on that project. And then the last component on the upward cost pressure is related to a few decisions that we've made. To ensure that we're mitigating total project risk and especially schedule risk. Just to ensure that we're hitting the milestones that we need especially on the front end of this project. And you've heard from me that we're hitting those so those have really paid well for us.

We prestaged equipment on winter season to ensure that we can knock out all the scope that we had originally premised. And, again, that's giving us the ability and the confidence to be able to guide you a bit more even on schedule. So to summarize, you know, we've moved from about 50% of our contracts being locked up at FID back a couple of years ago to now being well over percent of our facility contracts being secured. And a bulk of those are tied to market indices. That gives us transparency as the market moves and creates a lot of accountability with us and our business partners as we move through a project of this size.

And so this summer was the time for us to reconcile the actual inflation that we've been seeing over the last couple of years against forward-looking expectation. And you're hearing from me, we're in essence taking forward the type of inflation that we've been realizing forward into the next couple of years just to ensure that we're being conservative through this process. So looking ahead, again, back to execution, we've wrapped up detailed engineering that compels us to keep moving forward on the process module fabrication. That's a longer duration activity. It moves from this year into early 2027 in which we'll see lead those modules to the slope. Spend 2028 getting those into the Willow Development Area.

And Hooking Up And Commissioning Those For First Oil in 2029. So again, I'll wrap this up with an acknowledgment that we're just seeing really strong execution across the project, and that's foundational. It's paramount for us. In a project of this kind. And we're on track with all of our major scopes of work. And, again, all of this culminating in, and not just a guide on capital, but then our ability to provide an accelerated guide on first oil to the early part of '29.

Ryan Lance: I would just wrap it up, Neil, by saying that we're certainly disappointed that the costs are higher. Sorry. Wrap up Neil, but just saying I disappointed that the costs are higher, but certainly, we've taken measures across our portfolio to help mitigate the increase, and I think you see that in our first that's why we thought it was important to give some guide to, 2026. But the teams are executing well. And the projects really hitting all the milestones as Kirk described. We think it continues to be a world-class project. It's a huge driver of our free cash flow. Inflection that's coming over the next three to four years.

And really complete towards the end of the decade. And then the last thing I would say is we're going out probably with a bigger exploration program. We had in Alaska in a number of years. And it's that opportunity again to take advantage of this infrastructure that we're building for the long-term growth and development of the company and if we're right about our macro call and where we think the macro is going, we're gonna need this conventional oil to satisfy some of that growing demand around the world that we see. So it fits all of our ticks all of our strategic buckets as well.

So I know a long kind of explanation to the initial question out of that, but we thought it was important to provide some of that clarity and context around it to give you a cover when we know where we've been, we know where we're at, and we know where we're going.

Liz: Our next question comes from Arun Jayaram with JPMorgan. Your line is now open.

Arun Jayaram: Yes, good morning. Ryan, I was wondering if you could just maybe a quick follow-up on Willow. The F&D on the project goes up by $2 to $2.50 per BOE based on your updated outlook. I was just wondering if you could comment on how this impacts your project returns and just overall breakevens assuming, call it, a mid $60 Brent type of price.

Ryan Lance: Well, yeah. Thanks, Arun. Certainly, the estimate increase does impact the cost supply of this individual project. Going forward. It still fits well within our portfolio. It's still very competitive within the portfolio. And, again, we think longer term. We think about the future opportunities that are gonna come from this infrastructure, which is our history sitting on the North Slope. We've always, you know, the satellite discoveries that we get benefit from the infrastructure that we built, and we fully expect that to be the case. Going forward with Willow.

And then I'd remind you on the back end of this, the margins are still quite attractive because Alaska is, you know, a 100% oil sells at a premium to Brent typically on the West Coast of the United States. So that's why they even with maybe a little slightly higher F&D as you point out, you know, we still feel very comfortable with the margin, and it's competitive in the portfolio and it's gonna deliver a project for the company that will add to its future growth and development.

Liz: Our next question comes from Betty Jiang from Barclays. Your line is now open.

Betty Jiang: Hi. Morning, team. Thank you for taking my question. I want to maybe shift focus to the Lower 48. Just we talk a lot about the free cash flow for the major capital projects. But now they're seeing that the Lower 48 CapEx is also trending lower. In the '25 versus first half. And if you're staying here, CapEx will be lower year on year in '26 while still perhaps growing in that asset. So can you speak to the CapEx trajectory there, and how do you see the free cash flow progressing from the Lower 48?

Nick Olds: Yes. Good morning, Betty. You're exactly right. Maybe I'll take you back a little bit on the capital projection and a little bit of efficiencies that we're seeing within the Lower 48 portfolio. If you recall back in 2Q we achieved our level loaded integrating steady state program within the development strategy the Marathon assets. And so if you recall, we went from 34 rigs down to 24 rigs, so pretty significant reduction. We're still delivering kinda low single digit, growth, in that. So obviously, we're taking in stock that lower capital from going first half to second half, and you're gonna see that in the capital projections going forward.

Another key component of that, Betty, is a lot of around the efficiency improvements that we've seen getting into that level load steady state program which I can talk more about, but we're seeing you know, a significant improvement on drilling performance as well as our completions. That will continue into 2026. So if you kinda look at where we're currently at, we're probably gonna be on a run rate basis for 2026, something similar to 3Q for capital in 2026. And we will continue to have that level loaded steady state program roughly at 24 rigs in a frac crews going forward. As far as free cash flow, I'd probably let Andy talk about total company.

But we continue to see expansion with, again, all the efficiency improvements that we're seeing. With the productivity that you saw in 3Q. Really good strong quarter.

Andy O'Brien: Yes. Betty, it's Andy. I'll just jump in and sort of add on to what Nick was saying that so we feel it's important sort of on the free cash flow to talk specifically to the three LNG projects at Willow. But of course, there's a lot more than that going on in our company. And Nick just described what we've got with Lower 48 and the flexibility we have within the Lower 48 with that inventory if we wanted to ramp up that cash flow for growth. But even beyond that, there's other things that we don't factor into that. Free cash flow inflection.

Commercial, for example, when we talked about the commercial sort of strategy, you know, we've got put off at phase two, and we've got Rio Grande that we just mentioned today that will come on after Willow. That's gonna be sort of the 2030 time frame. So there's a lot more going on in the company than just those four projects. We've got other things going on sort of, you know, in Canada, you know, in Alaska, you know, around some other international assets, but we just wanted to keep line of sight on this specific free cash flow inflection. And then we obviously have the ability to add to that.

Liz: Our next question comes from Steven Richardson from Evercore ISI. Your line is now open.

Steven Richardson: Hi. Thanks. It's a good segue from what you just mentioned about some of the other assets. I was wondering if you it sounds like you've got some good visibility on some of the organic and capital efficient opportunities in the portfolio. In Alaska, I was wondering if you could you know, talk about some of the regulatory and permit changes and how you're thinking about incremental op opportunities either in legacy ops or extending the resource at Willow.

And then if I could, you know, if you could maybe talk a little bit about Surmont, you've talked about incremental steam potential, but, you know, I had to understand that there's some other things that you could be doing now that you've got your arms around that asset. And to improve it with minimal capital. Thanks.

Ryan Lance: Yeah. Thanks, Steve. I'll take that one. I think it's yeah. Andy's answer to the last one, it's you know, this updates a lot about Willow and some of the major projects to give the market some clarity as to what we have going on there and some clarity into our free cash flow growth and it doesn't really address and assume some of the things we have that we're studying inside the portfolio as well, and you mentioned a few of those. I think we do have a strategic question longer term if our call on the macro is right. Then where is the conventional oil gonna come from to satisfy the growing demand?

And we see that demand growing clearly million barrels a day or so per year for the foreseeable future. We look inside the portfolio, it's not only what we're doing in Willow and what we believe are gonna be the added sort of pads that we can develop there. And to your point, we're working with the administration to identify some ways to streamline the permitting. I think you saw an early read of that with the new rules that are coming out for development in NPRA. That's just sort of the start. There's more things coming will give us what we think is gonna be a lot more clarity to faster permitting approvals coming in Alaska going forward.

So watch that space as we move on and hopefully not only make it more formidable and easier and faster, but also more durable with changing administrations. And then your other point, yeah, when we look that's just Alaska. And I commend the team also managing the base. There's a lot of activity going on the base side in Alaska as well. We have flexibility at the Montney asset to ramp up should the call on crude be required to go do that. You mentioned Surmont. We're right now debottlenecking that plant as we speak. That we own a 100% of that plant, we were able to make some investments in there that our previous partner were not approving.

So we're taking the gross productive capacity of the plant up today, and then looking at future. Can we add a few steam generation capacity to accelerate some of the development that we have with the huge resource that we have around Surmont. That's very competitive in a all at sub $40 cost of some. So when we look at the whole portfolio, and you look at the deep inventory we have in the Lower 48, combined with the other conventional opportunities we have around the world, we're really set up for decades of growth. In this business.

I like where we're at, and I like the portfolio and what we're doing today and the optionality that it creates for the company over the short, medium, and long term.

Liz: Our next question comes from Lloyd Byrne with Jefferies. Your line is now open.

Lloyd Byrne: Hi. Thanks. Good afternoon, everyone. Ryan or Andy, I was just hoping you could spend a little bit more time on the OpEx. I mean, $400 million improvement, and in light of it kinda being the second cut this year, it just what's changing? Maybe remind us of the big factors that have improved and whether you can improve it further. Thanks.

Andy O'Brien: Yeah. Thanks, Lloyd. I can take that one. Know, I think at the highest level, the first thing I would say is that we're executing really well in, you know, with our cost and capturing the savings. And as you said, that's why we've been able to reduce the guidance for the second time this year. But going into a few specifics, I would remind people that we've already achieved now 75% of the Marathon synergies that we were talking about over the prior quarters. That's in our cost and we'll have that basically completely into our cost by the time we get sort of to the end of this year on a run rate basis.

So you know, we're exceptionally pleased with how smoothly that's gone in basic delivering on those cost reductions that we've previously talked about. And then as we look you know, to 2026, know, and you know, stepping the cost down again, as you said, so that's basically getting the full year benefit of some Marathon synergies that we've I just described. But then we expect to capture a meaningful amount of the cost improvements that we announced on the last quarter call. You know, and we you know, where that's basically gonna drive some pretty meaningful reductions in our costs you know, as we go through next year.

You know, it's you know, that account of the key things, when we think about sort of how we reduce costs, we have sort of mindset that this is continuous improvement. So we absolutely sort of, you know, challenge ourselves to sort of look at how we can basically continue to reduce those costs over time. But I think we're very pleased with sort of how we're doing that and sort of how that's showing up in our bottom line.

Ryan Lance: And I would add, Lloyd, you know us well. These reductions aren't conflated with capital kinds of things. They're not due to dispositions. In the portfolio. We don't have 30 lines of reconciliation because the net doesn't ever show up. And they're not cumulative. These are costs that'll show up on our bottom line, and as I've said before, just watch us every quarter and you'll see them materialize. They'll be real and they'll head straight to the bottom line and to our free cash flow inflection that we've been talking about for the next number of years.

Liz: Our next question comes from Scott Hanold from RBC Capital Markets. Your line is now open.

Scott Hanold: Hey. Good morning. Thanks. I know it's always challenging to provide forward guidance with some uncertainty on commodity prices. So appreciate the details on '26. Looking at total and capital, it does appear similar to consensus numbers. But you know, there does appear to be a variance to your oil guide relative to consensus. And was hoping you could help us walk through, you know, where we might have, you know, sort of missed that and you know, we do understand there's a lot of complexity given the senior diversity of assets and other things like Surmont post payout. But I was wondering if you could walk us through some of that.

Andy O'Brien: Hey, Scott. This is Andy. I'll get started with a couple of points here, and then maybe Nick can provide a bit more detail on the Lower 48 for us. Just a couple of things I'd say is that, you know, if you look at our third quarter, you know, at the total company, we're at a mix of about 53% oil. And this is the first quarter now where we have the full impact of so much that you just referenced. So we now have a higher royalty in Surmont. So the third quarter is a pretty good mark basically as we think about 2026.

And you know, we provided guidance and hope you found that helpful where we've now provided guidance basically for an oil split and where we're basically forecasting 26% to be about that 53% for the total company. That does include sort of the bitumen impact of higher royalties and so on. And then specifically to Lower 48, we're guiding, you know, about 50%, for the Lower 48. And then just one final point I would make before, you know, Nick can maybe comment on the Lower 48 is when we provided our 26 guidance of 0% to 2% range, for BOEs. That's also a good range for how we're thinking about oil as well.

So I think we've tried to sort of guide a bit more on this time as you say, we recognize as you as you, you know, provided for us upfront that you know, a lot of moving parts here, but you know, across the portfolio. But that 53% for the total company we think it's a good mark for next year. Maybe Nick just had a few comments on Lower 48.

Nick Olds: Yes. Thanks, Andy, and good morning, Scott. If you look at 3Q Lower 48 oil mix, we're around about 50%. If you compare that to 2Q, it was about 50.5, and that was in line with our expectations and our development plan. Going forward. As Andy mentioned, we're guiding to oil mix at 50% when you look at 2026 forward. And, again, that's simply an output of our plan. An output of our development plans where we're developing in the various basins. Now as a reminder for the group within the Delaware, that is our most significant growth driver within the Lower 48. So it shouldn't be a surprise to this group that oil mix will trend in that direction.

It's low cost to supply, higher gas content, but very good strong oil content and good returns. Another key component to think through is got two decades plus of drilling inventory at current rig activity levels. In the Delaware. It's a pure leading opportunity set out there. Now one other component that need to through is that oil mix can fluctuate depending on the relative contributions from these basins as we drill in different areas. So you might have some higher oil mix and some more oil mix and variations from quarter to quarter. But overall, as Andy mentioned, 50% on Lower 48 oil mix going forward.

Liz: Our next question comes from Doug Leggate from Wolfe Research. Your line is now open.

Doug Leggate: No. Thank you. Guys, I'm gonna try very hard to make this one question, but I'm hoping you can maybe help us navigate the moving parts a little bit. My question is on is principally on Willow and just the CapEx, what happens after Willow. But it's really about the evolution of your dividend breakeven because I think the Willow news has overshadowed the other big news, which, of course, was your dividend increase. So I guess my the way I would try and phrase the question is, how damaging is the increase in will of spending to the cash cadence of the cash flow coming back.

And then I guess my point specifically is, you get qualified CapEx deductible and taxes in Alaska. It's pretty advantaged. So can you walk us through how big a deal this really is? And what happens to the dividend breakeven as Willow comes online.

Andy O'Brien: Hey, Doug. This is Andy. I can try and step through that. I think you sort of half answered the question for me in terms of sort of how this works on a tax basis. And Ryan touched on this also in the prepared remarks, and the way I would look at it sort of at a total company level, is, you know, our breakeven is coming down and it's coming down pretty substantially. Just right now, if think about where we are right now, our breakeven this year so just on CapEx is in the mid-40s. You'd add another 10 to that for the dividend.

Just from what we've described today from what we're doing from 25 to 26, yep, that brings our breakeven down in a bit itself. Know, 2 to $3. So we're on this trajectory of yes, cash flow inflection is going in one direction, which is great, and then our breakeven is also coming down which is great. And as Ryan said in his prepared remarks, that's going to continue to happen where we're gonna go all the way down to being in the low thirties on a capital breakeven by the time the time 8% and this is now the fifth year of us having top quartile growth. Of the dividend. And versus the S&P 500.

And we feel very confident with that breakeven that continues.

Ryan Lance: Yes. And I would add as well, Doug. You know, look, it's and it's sustainable given the breakeven coming down is Andy described. You know, the dividend is representing a lower portion of our total cash flow in terms of our distribution back to the shareholders. So now to give the shareholders and stakeholders in the company a lot of comfort and conviction that we can continue to deliver top quartile S&P 500 dividend growth in the company well into the future given the projects that we're executing, the cost supply of those projects, and the free cash flow growth we're gonna see coming out of the company.

So it's quite sustainable and leaves us room to buy back some of our shares, which were leaning into quite a bit right now.

Liz: Our next question comes from Bob Brackett from Bernstein Research. Your line is now open.

Bob Brackett: Yes. Good morning. As much as I'd love to ask a few on Willow, I'll change the topic a bit. And that is to talk about the 2026 guide at zero to 2%. And we've seen other large E&Ps and integrators with similar sorts of guides in a backdrop where WTI is sitting below 60. So can you talk about what macro world you envision or which you plan for that we're going to see next year? And how does that inform that capital guide and production guide?

Ryan Lance: Yes. Thanks, Bob. I think we like to say we have a lot of flexibility in the company. Production is kind of an output of our plans. We kinda said sort of a constant level loaded scope within the Lower 48. Nick talked a lot about what that means for kind of the production growth we see out of coming out of that. Our view of the macro is supportive. Again, we kinda set this at a $60 WTI to your point. WTI is trading a little bit below 60 at this moment in time. Our call would be probably seeing some inventory builds. We saw some this last week.

We'll see how it continues onshore in the OECD countries, but we price these some downside pressure coming through the latter part of the ending part of this year and into maybe the first part of next year. So but that's why we have a balance sheet. That's why we have cash on the balance sheet. We wanna continue to fund our programs. We came out with a zero to 2%. We think that sort of makes a lot of sense with the macro that we're seeing today. But it also is informed by the medium and longer term, which we're quite constructive on today.

Again, we see about a million barrels a day of demand growth not abating itself throughout this decade and in well into the next decade. And we think there's gonna be a call on crude and even a call on conventional crude depending on what you believe the unconventional supply coming out of the US is gonna look like if these kinds of prices or even elevated prices. So we see some modest growth in the unconventionals continuing maybe flat to slightly some slight growth into next year depending on the price.

But I think it sets up well to be a bit more reflective as we go into 2026, which is what we've tried to show with our zero to 2%. But remind everybody, we've got a lot of flex in the portfolio both ways. We have opportunities to reduce more CapEx. Should we think that's the need, we can use the balance sheet. Should we decide to do that, then, obviously, we've got opportunities to ramp up on the other end as well.

So we just think we have a lot of flexibility in the company, but I think this is a good place to start based on sort of how we view the near-term macro and where it's been developing.

Liz: Our next question comes from Geoffrey Lambujon from Tudor Pickering Holt. Your line is now open.

Geoffrey Lambujon: Good morning and thanks for taking my question. I'll bring it back to Willow if I could and want to say I appreciate the detail. Earlier in the call that spoke to the breakdown there on the refreshed expectations. Can you also talk about the confidence level in the updated range and essentially what might be locked in from here? It'd be great to just get a sense for what flexibility there might be up or down. Things change enough over the course of the build-out or if the wider range you have now captures the most likely scenarios in your view, it's more a function of where you end up within that range. Thanks.

Kirk Johnson: Yeah. Good morning, Jeff. Yeah. Again, I would say we're winding back here a little bit. We recognize there was quite a bit of inflation coming out post-COVID over the couple of years leading up to our taking FID in late 2023 and actually seeing that abate a bit in late 2023, which is why we took a view of just a couple percent. And we felt like, obviously, the monetary actions globally were gonna knock that back a little bit. And so, again, we took that view at the time, and this is just a really good time for us being roughly halfway through the project. To reconcile what we've been seeing over the last couple of years.

And as you know, it's across labor markets and engineered equipment. We've definitely seen movement. Which is much more on the average of four and a half to 5%. And that's been actual and realized you can certainly see the data yourself across the last couple of years. Now you know, sitting here today, we're seeing inflation rates abate. A bit. We're starting to see inflation again in the three, three and a half percent. But candidly, we're taking a view that this compounding inflation could based on the contracts that we have tied to market indices, could continue. In that 4% to 5% range.

And so we've largely budgeted for that for the next three plus years of the project just to ensure that you know, we're not kind of falling back into prior assumptions in FID. So I would say we've got a lot of confidence in the obviously, in the way we're putting this capital guide forward here at this time. And again, able to stand here in this position with that confidence because the team is executing just so well on the project. And we're not seeing schedule slip. We're not seeing other challenges. Certainly, upward cost pressure, you're not seeing me talk about scope discovery.

This is really about inflation across the broader market, and we've taken a conservative view for the next couple of years. So yeah, confidence in how we're pushing this out here today. And again, just pleased with how the project's moving forward and here for the next couple of years.

Liz: Our next question comes from Paul Cheng from Scotiabank. Your line is now open.

Paul Cheng: Ryan, I think as you mentioned earlier, that you think that they maybe increasing call on oil even on the conventional. And when we're looking at over in over the past ten years, I think you guys have drastically reduced your dependence on exploration. Because you have such a great profile in the Lower 48? And as the shale oil is maturing, how should we look at it? Would you think that you still have such a huge portfolio that you really don't need to increase your exploration effort. And you can just rely on that on the share over there to continue with pace your resource, your production.

Or that you think the challenge on the longer term is really enough that we need to start maybe increasing the effort given it's a long cycle business.

Ryan Lance: No. Thanks, Paul. I think you bring up I guess there's probably an industry-wide macro question around that. Are we investing enough industry-wide on the exploration side? And if we lost some of that muscle inside the industry for that and large project execution for that matter. And there's probably a bit to that from the industry side.

Speaking specifically to our company, you're right after kinda the early 2000 time frame when we first got into the Eagle Ford and saw the grown our unconventional position inside the company and then really changed the portfolio pretty dramatically over the last number of years to really focus on those low cost of supply opportunities and resources that we now have captured inside the company, it has put a less reliance on exploration. But I remind everybody, we continue to spend $200 to $300 million a year on expiration to continue to feed some of the legacy assets we have around the company.

And years past, that's been in Malaysia, been in Norway, we've moved that around throughout the years depending on some of the activity level and the opportunity set that we find. And we're doing it again next year because we're focusing most of that expiration probably up in Alaska to support the Willow development and then get the company in a position to be able to feed that infrastructure that we're building out there for decades to come. So it's part of a redirection of exploration, but we've been able to do that within that $200 to $300 million allocation inside the company.

We just spud a well in the Outway Basin of Australia to try to find more gas that we can bring into Australia. So this is not just a one area where we're appraising the Discoveries for Google that we had in Norway. You know, a year or so ago. So we are spending some of that money. To date, it hasn't captured a higher capital allocation inside the company because we've been able to get everything we wanted to get done for that $200 to $300 million. But I think you're right. Macro wise within the industry, you're seeing a lot more of that.

We've just been blessed with a we're a resource-rich company in a resource-starved world, it looks like, going forward. So I think we're uniquely positioned relative to many of our peers in the industry with having to consider significant ramp-ups in that capital allocation.

Liz: Our next question comes from Charles Meade from Johnson Rice. Your line is now open.

Charles Meade: Yeah. Good day to you, Ryan and Andy, and to the rest of the Conoco team there. I'd like to ask a big picture question about your global LNG strategy. And, you know, you guys make this distinction between resource LNG and commercial LNG. And then I wonder if you can talk about how those two how you think differently about those two pieces of the business, how they complement each other, and perhaps how they compete with each other. And maybe wrap into that.

You know, one can make the argument that with the amount of resource you guys have in the Lower 48 that you know, that make a distinction between resource LNG and commercial LNG is kind of a valid argument in your view. Distinction without a difference and maybe comment on whether that's a

Andy O'Brien: Hey, Charles. This is Andy. It's a great question and a big question, as you say, in terms of sort of comparing the two and how we think about them. So I'd probably go maybe back all the way to the beginning. We've been in the LNG business really since the 1960s. We were involved in basically sort of inventing this business. So kinda know a thing or two about it.

And we traditionally sort of until recent years had what I would call the sort of the resource LNG, sort of the rich LNG business where you know, it's been very much about finding a stranded gas asset and you know, you find a gas asset, you find people who will buy the LNG, then you build LNG facility. And off you go. That's kind of where this industry, you know, was for years. And, we've been a big player in that with our Australia asset and our Qatar assets over the years. And that has served us really well.

But as you fast forward sort of to what's happening in, you know, in the Lower 48, it's a little bit of a different model in the and you kind of started to touch on this where you've got so much gas in the Lower 48, that you don't need to treat it like you know, facility by facility approach where you've got the stranded gas that you're trying to tie to one facility.

So it's the whole model is different effectively in the you know, you're trying to take this gas in the Lower 48 and know, our strategy is pretty simple, you know, where we're trying to basically take know, what we think is low-cost supply North American gas and get ourselves access to international pricing in TTF and JKM. And that's exactly what we're positioning ourselves to do. We've made great progress in doing that with as I talked about in the prepared remarks, the five MTPA have put up and phase one that we've now fully placed.

And then we're now moving on to Port Arthur phase two where we took four MTPA and another, you know, one MTPA at Rio Grande. So you know, we're trying to basically get ourselves in a situation where we you know, we can basically convert Lower 48 gas into international pricing. And what I would remind, you know, everybody is that we're also in a position where this commercial strategy complements our business so well, we produce over two BCF a day in the Lower 48, and two Bcf a day in round numbers is about 15 MTPA. So it's you know, it also works as a natural hedge to our Lower 48 gas exposure.

So I back to you first off because I don't really see them as the resource LNG competing with what we're doing in the Lower 48. They're kind of different models, but we've certainly been able to learn from the resource LNG, and that's why we've been able to sort of implement the strategy we are doing, basically, where we're trying to control the entire value chain and you only can do that with our global size and scale you know, and that's how we basically think we capture the economic rent. So hopefully that helps sort of frame up how we think about the difference between the two. But I don't not like an either-or choice for us.

We think that they both serve a really important role and where we're happy to be playing in both as you can see with NFE and NFS on the resource side. And what we're doing on the commercial side. With Port Arthur and the other announcements we've made today.

Liz: Our next question comes from James West from Melius Research. Your line is now open.

James West: Hey. Good morning, guys, or I guess, to good afternoon. I wanted to follow-up on the LNG question. Obviously, the strategy is pretty clearly defined here. You had a lot of commercial movement. During the quarter, you're at 10 MTPA. Now I think you've said in the past 10 to 15 is kind of a range. Are we at a point where maybe you pause and digest? Or do you lean in and go up to that 15?

Andy O'Brien: Yeah. I'd say very briefly, our strategy remains unchanged. We're executing exactly what we said. You know, the 10 to 15 MTPA is a size that we feel very comfortable about. It gives us the size that we want to be able to optimize our portfolio, be able to divert cargoes, as I mentioned in the prior question, be able to control really the value chain. And I don't think anything's really changed there that 10 to 15 is kind of what we're looking to fill out right now.

Ryan Lance: And I think, James, it's also a function of not getting too much commitments on the front end, make sure you can place it on the back end. So we're being deliberate about that. And you know, if we get more opportunity for low liquefaction costs, opportunities, will add more to the 10 million MTA, but we gotta back it up with regas on the other end have a plan for it. So we're being deliberate now that we've reached that 10 million ton mark.

Liz: Our last question comes from Kevin McCurdy from Pickering Energy Partners. Your line is now open.

Kevin McCurdy: Hey. Thank you guys for fitting me in. I want to come back to Slide seven for a moment on the incremental free cash flow. And I've known you've shown I know that you've shown this before with the $4 billion of free cash flow from Willow. But I think that's quite an eye-catching number. I was wondering if you could provide anything kind of high level on how you get there in terms of margins, productions, maintenance CapEx in that first year? And if that and also to ask if that's a fairly good number to use heading forward for Willow. Post 2029.

Kirk Johnson: Yeah. Hi, Kevin. Good morning. This is Kirk. So certainly, as you saw in the waterfall and the details in the supplementals, on Willow, you can really take it directly from that. So as we compare against what was a historical, and expected spend, here this year, of just over $2 billion as mentioned by Andy and the prepared remarks. We're expecting that here on the Willow Capital spend here this year. And then that moves down plateaus for the next couple of years. And then on sustaining capital, post first oil, we're expecting to spend roughly half a billion dollars in just continued development drilling for the Willow project. Obviously, we're starting predrill.

We've got some predrill planned in 2027. And then that will extend. And that predrill is all baked within our total Willow project spend. But then post first oil, that half a billion dollars. So in essence, what you're seeing is this inflection downward of capital from roughly $2 billion to an average of half a billion. First oil. And then at first oil, getting the CFO associated with, again, why we like Alaska. A 100% oil. Sales. It's Brent premium. And again, that is the balance then of the $4 billion free cash flow improvement against a reduction of roughly $1.5 billion on CapEx.

Ryan Lance: And I just remind Kevin that you sell the prices that's assumed at $70 prices and you know, we've given a sensitivity to that as well in the materials. So well, let me thank everybody for participating today. Just a few summary comments. You know, we continue to execute well. We're improving our plan, and we're well positioned for a strong 2026 as evidenced by the new guidance we provided today. And I'd say, you know, the team continued to find a lot of ways to enhance value in what we think is a differentiated investment thesis. We have an unmatched portfolio quality. We've got a leading Lower 48 inventory depth.

Combined with attractive longer cycle in the LNG in Alaska that we've described today in quite a bit of detail. And we continue to have a strong track record of returns on and of our capital. And that's all leading to a sector-leading free cash flow growth profile that takes us all the way to the end of this decade. So thank you all for your interest in ConocoPhillips, and we appreciate the question.

Liz: Thank you, ladies and gentlemen. This concludes today's conference. Thank you for participating. You may now disconnect.

Where to invest $1,000 right now

When our analyst team has a stock tip, it can pay to listen. After all, Stock Advisor’s total average return is 1,052%* — a market-crushing outperformance compared to 193% for the S&P 500.

They just revealed what they believe are the 10 best stocks for investors to buy right now, available when you join Stock Advisor.

See the stocks »

*Stock Advisor returns as of November 3, 2025

This article is a transcript of this conference call produced for The Motley Fool. While we strive for our Foolish Best, there may be errors, omissions, or inaccuracies in this transcript. Parts of this article were created using Large Language Models (LLMs) based on The Motley Fool's insights and investing approach. It has been reviewed by our AI quality control systems. Since LLMs cannot (currently) own stocks, it has no positions in any of the stocks mentioned. As with all our articles, The Motley Fool does not assume any responsibility for your use of this content, and we strongly encourage you to do your own research, including listening to the call yourself and reading the company's SEC filings. Please see our Terms and Conditions for additional details, including our Obligatory Capitalized Disclaimers of Liability.

The Motley Fool has no position in any of the stocks mentioned. The Motley Fool has a disclosure policy.

Disclaimer: For information purposes only. Past performance is not indicative of future results.
placeholder
US Dollar Index Price Forecast: Rally pauses above 100.00 despite Fed dovish bets ease furtherThe US Dollar Index (DXY) trades 0.18% lower to near 100.00 during the European trading session on Thursday.
Author  FXStreet
13 hours ago
The US Dollar Index (DXY) trades 0.18% lower to near 100.00 during the European trading session on Thursday.
placeholder
Galaxy lowers Bitcoin forecast to $120K due to AI and goldGalaxy Digital lowers its year-end bitcoin target from $185,000 to $120,000 due to slowing momentum in the ‘maturity era’ of the bitcoin market.
Author  Cryptopolitan
13 hours ago
Galaxy Digital lowers its year-end bitcoin target from $185,000 to $120,000 due to slowing momentum in the ‘maturity era’ of the bitcoin market.
placeholder
What Altcoins Whales Are Buying After the Early November Crypto Crash?The early-November crypto crash caught the market off guard, contradicting expectations of a strong, bullish month.
Author  Beincrypto
13 hours ago
The early-November crypto crash caught the market off guard, contradicting expectations of a strong, bullish month.
placeholder
U.S. Stock Market Opinions Diverge: Will the Market Rise or Fall Going Forward?U.S. stocks have recently pulled back from their peaks, and investor forecasts for the path ahead have sharply diverged.
Author  TradingKey
13 hours ago
U.S. stocks have recently pulled back from their peaks, and investor forecasts for the path ahead have sharply diverged.
placeholder
EUR/USD picks up from three-month lows as risk sentiment improvesEUR/USD posts moderate gains for the second consecutive day on Thursday, trading at 1.1505 at the time of writing, up from the three-month lows at 1.1468 hit earlier this week.
Author  FXStreet
14 hours ago
EUR/USD posts moderate gains for the second consecutive day on Thursday, trading at 1.1505 at the time of writing, up from the three-month lows at 1.1468 hit earlier this week.
goTop
quote