Image source: The Motley Fool.
Thursday, February 19, 2026 at 12 p.m. ET
Need a quote from a Motley Fool analyst? Email pr@fool.com
Fortuna Mining Corp. (NYSE:FSM)'s quarterly results reflect momentum in both production growth and cost control, with high liquidity and net cash increasing operational flexibility for ongoing development. Management detailed precise milestones for Diamba Sud and Seguela, allocating robust capital to accelerate project timelines and secure early procurement, while emphasizing the role of higher gold prices in driving year-over-year earnings and cash generation. The company provided explicit guidance on the sequencing of future capacity expansions, stated annual exploration budgets, and outlined the mechanics of planned throughput increases and underground development, indicating a firm ability to manage both organic and external risks through disciplined investment and resource conversion strategies.
Jorge Durant: Thank you, Carlos. Good morning, and thank you for joining us today. I'll start very briefly with the quarter before moving to our growth outlook. In the quarter, we delivered record adjusted net income of $0.23 per share, generally in line with analysts' consensus. Net cash from operations before working capital adjustments was a strong $0.48 per share, exceeding consensus estimates of $0.43. We also generated record free cash flow of $132 million for the quarter and again, record $330 million for the full year, highlighting the strength of our operations and balance sheet, which ranks amongst the strongest in our peer group, with over $700 million in liquidity and a net cash position of approximately $380 million.
With that context, let me turn to the more important part of the story now, which is growth and value creation. As we have stated, our objective is clear: to grow Fortuna to more than 0.5 million ounces of annual gold production from long-life assets, achieving this over the next 24 months. This will represent approximately 65% growth from current production levels. Importantly, this is growth that we control. The ounces are already contained within our mineral inventory across advanced projects in our portfolio. As this production comes online, we expect it to translate into meaningful growth in free cash flow per share, supported by scale, asset quality, good geographic distribution and capital discipline.
The delivery of this growth is driven by 2 core assets: Diamba Sud in Senegal and Seguela in the Ivory Coast. Starting with Diamba Sud, the project continues to advance on a fast track approach towards a formal construction decision in midyear, aligned with the publication of the feasibility study. This morning, we released an updated mineral resource estimate, showing a 73% increase in indicated resources to 1.25 million ounces of gold, which will form the key foundation for the study. For 2026, we have approved a $100 million budget at Diamba Sud, with $67 million of that allocated to early works, which include the camp facilities, major excavations and other enabling infrastructure.
We began breaking ground this week and we filed our exploitation permit application earlier this month, marking important execution milestones. Mineralization at Diamba remains wide open, and we continue to carry out aggressive drilling in parallel with project development activities as we pursue further resource growth while growing, continuing and derisking project time line. Turning to Seguela. We're preparing for the next phase of growth through a plant upgrade study currently underway, evaluating throughput expansion options that potentially take the mine to 200,000 ounces of annual production. This work builds on recent reserve growth and position Seguela to deliver higher production and cash flow from an already high-quality long-life asset.
In summary, Fortuna's growth to over 0.5 million ounces is visible, controlled and executable, supported by a strong balance sheet, a sound base of mineral resources and reserves and a clear focus on per share value creation. With that, I'll turn the call over to the operating team. David, do you want to share your update?
David Whittle: Thank you, Jorge. Seguela delivered another strong quarter and for the second consecutive year, exceeded the upper end of production guidence. This consistent outperformance reflects the strength of the operation and the quality of the asset. Encouragingly, recent exploration drilling results providing further momentum, presenting opportunities to increase production levels beyond the current mine plan assumptions. At Diamba Sud in Senegal, the project continues to advance on schedule, early works programs have been approved, key contracts have been tendered and awarded and the project team is mobilizing in preparation for the next development phase.
Importantly, during the fourth quarter, no significant incidents were recorded across our West African operations, underscoring our commitment to maintaining a safe and healthy workplace for all personnel. At Seguela, we produced 36,942 ounces of gold in the fourth quarter, consistent with prior quarters and ahead of the mine plan. For the full year, production totaled 152,420 ounces, exceeding the upper end of guidance by 4%. Mining during the quarter totaled 340,000 tonnes of ore, at an average grade of 3.71 grams per tonne gold, along with 3.92 million tonnes of waste, resulting in a strip ratio of 11.5:1.
The processing plant created 410,000 tonnes of ore at an average grade of 3.01 grams per tonne gold, with throughput averaging 214 tons per hour. Ore was primarily sourced from the Antenna Ancien and Koula pits with waste mining also commencing for the Sunbird pit. The Sunbird underground project continues to advance strongly. Based on drilling completed through to the end of June 2025, we declared a reserve of just over 400,000 ounces. During the second half of 2025, 5 diamond drill rigs were allocated to Sunbird, delivering excellent results that support further resource growth.
Given the strength of the Sunbird underground and the incorporation of Kingfisher Open pit into the life of mine plan, we've identified an opportunity to increase plant capacity. Like a [ podium ], the original plant builder has been engaged to evaluate expansion options, targeting throughput of between 2 million and 2.5 million tonnes per year. Early indications are positive and we expect to complete the study early this year. So again a strong operational performance translated into a cash cost of $710 per ounce of gold for the quarter and $679 per ounce for the year.
AISC was $1,576 per ounce of gold for the quarter and $1,560 per ounce for the year, at the midpoint of guidance, despite an $86 per ounce impact from higher royalties lead to increased gold prices. Cost discipline remains a clear strength of the operation. In 2026, exploration drilling will continue at pace, with increased focus on infill drilling and step-out testing along [ stopes ] and at depth at Kingfisher as well as continued evaluation of additional targets across the 35 kilometers strike length from the Seguela [ land ] package. Drilling at Sunbird underground will also continue as we advance technical studies and progress permitting activities. Capital has already been allocated for long-lead underground mining equipment.
Turning to Diamba Sud, exploration, environment permitting and feasibility work advanced meaningfully during the quarter. Government approvals were received for early works programs the ESIA during its final stages of approval. Following the rainy season, drill rigs were remobilized at SEMARNAT and other deposits with continued positive results, further strengthening our confidence in this already robust package. Thank you. Back to yourself Jorge.
Jorge Durant: thank you, David. Now sure, Cesar will share the update on Lat Am operations. Cesar, please?
Cesar Velasco: Thank you, Jorge, and good afternoon, everyone. Our Latin Africa operation delivered resilient performance in 2025 with no reportable safety incident, supported by strong production execution during the first 3 quarters of Lindero and consistent results at Caylloma throughout the year, where base metal production exceeded the upper end of guidance. Fourth quarter results at Lindero by impacted by mechanical downtime in the crushing circuit, which affected full year production. At Lindero, full year gold production totaled 87,489 ounces, approximately 6% below the lower end of guidance, affected entirely by the fourth quarter production, which totaled 19,201 ounces of gold, driven by 2 independent mechanical interruptions during the same period.
An engineering review identified the structural fatigue risk in the primary crusher foundations. To address the root cause, we have approved a 35-day foundation replacement schedule for late March 2026 at an estimated cost of $2.2 million. Ore is being pre-stockpiled to maintain stacking continuity during the repair. This has been fully considered within our production plan and guidance for the year. From a financial perspective, Lindero generated $294.2 million in annual gold sales and EBITDA margin remained strong at 57% to sales. Cash cost of $1,117 per ounce of gold for Q4 and $1,132 for the year, well within guidance range.
Q4 all-in sustaining cost improved to $1,639 per ounce of gold due to lower sustaining capital and reduced stripping, offset by the impact of maintenance interventions and temporary crushing solutions. AISC for the full year of $1,716 per ounce within guidance range. We are currently conducting approximately 6,500 meters of diamond drilling below the pit bottom, where mineralization remains open at depth. The objective of this program is to upgrade and estimated 40,000 ounces of inferred resources to the indicated and measured categories. These resources are located beyond the limits of the current final pit design and the resources pit shell. Lindero remains a high-margin, long-life mine with strong fundamentals.
Now turning to Caylloma, the operation continued to deliver consistent and disciplined performance throughout 2025. In the fourth quarter of 2025, Caylloma produced 250,000 ounces of silver at an average head grade of 65 grams per tonne, maintaining production levels in line with the previous quarter. Zinc and lead production totaled 12.1 million and 8.4 million, respectively, at an average head grades of 4.32% zinc and 2.95% lead. Production remained steady quarter-over-quarter as mining continued from the same levels and stopes, supporting predictable milled feed and recoveries. For the full year production of [Technical Difficulty]
Operator: Ladies and gentlemen, please remain on the line while we reconnect the speaker to the conference room. Thank you for your patience. Once again, ladies and gentlemen, please remain on the line while we reconnect the speaker to the conference room. Once again, ladies and gentlemen, please remain on the line while we reconnect the speaker to your conference. And Carlos your line is connected. Your line is live.
Carlos Baca: Yes. We're back. Okay.
Jorge Durant: I think we can move on to the financial summary with the CFO. Luis, please go ahead.
Luis Durant: Thank you. So attributable net income for the quarter was $68.1 million or $0.22 per share. On an adjusted basis, excluding noncash charges, net income was $71.3 million or $0.23 per share. This represents a significant increase over the $0.06 reported in Q4 of 2024 and the $0.17 in Q3 of 2025. Year-over-year, that increase was primarily driven by higher gold prices. We realized an average price of 4,166 per ounce, an increase of over $1,500 per ounce, while consolidated cash costs rose only marginally by 5% to $971 per ounce. This pricing benefit was partially offset by lower production volumes stemming from the HPGR downtime at Lindero in December, as referenced by Cesar.
Compared to Q3 of 2025, the $0.06 increase in EPS was similarly driven by a $700 per ounce rise in realized gold prices. I will take a couple of minutes to make a few other comments pertaining to certain items of our annual results. We recorded $26 million in general and administration expenses for Q4, which includes $6.9 million in stock-based compensation. This total is $9.5 million higher than Q4 of 2024. This increase was driven by 2 main factors: $5.3 million related to higher stock-based compensation due to our year-over-year share price appreciation; and $3.5 million in higher site level G&A, primarily due to timing of expenses. A full breakdown is available on Page 10 of our MD&A.
Looking ahead, we expect quarterly G&A, excluding stock-based compensation to range between $14 million and $16 million across our corporate and site operations. Continuing with G&A, full year expenses totaled $97.7 million, an increase of $29 million over 2024. About 2/3 of this variance, approximately $20 million stems from stock-based compensation, driven once again by the year-over-year appreciation of our share price. We recorded a foreign exchange loss of $2.9 million for the quarter and $7.8 million for the full year. The annual figure includes a $13.8 million realized foreign exchange loss, primarily driven by our operations in Argentina.
Notably, over $6 million of this realized loss stemmed from cash balances held [ in country ] during the first half of the year. However, this was fully offset by hedging strategies we implemented to protect the U.S. dollar value of our local currency. Interest and finance costs for the quarter were $2.6 million, which is $3 million lower than Q4 of 2024. And for the full year, interest costs totaled $12.3 million. This is a $12 million decrease from the previous year. This improvement was driven primarily by a significant increase in interest income which rose to $14.5 million in 2025 compared to $3.7 million in 2024, reflecting our growing cash balances.
Finally, on the income statement, our effective tax rate for the fourth quarter was 33%, while the full year 2025 rate was 26%. These figures reflect the statutory tax rates in our operating jurisdictions as well as withholding taxes associated with the repatriation of profits. Looking ahead to 2026, we expect our effective tax rates to average between 30% and 33%. Moving to cash flow and liquidity. Our total capital expenditures was $44.5 million for the quarter and $178.1 million for the full year. Of the annual total, $109 million was dedicated to sustaining capital and $69 million to growth initiatives.
This growth spend included $48 million for exploration across Diamba Sud, our operating sites and greenfield initiatives, along with $14 million to advance the Diamba Sud project. Free cash flow from ongoing operations, which accounts for sustaining capital reached $132 million for Q4 and $330 million for the full year. This represents an EBITDA conversion rate of 84% and 60%, respectively. We ended 2025 with $704 million in total liquidity, a $327 million increase over 2024, driven by our strong operating results and the sale of Yaramoko earlier this year. Back to you, Jorge.
Jorge Durant: Carlos. That's all for management, and we can open the floor for Q&A.
Operator: [Operator Instructions] Your first question is coming from Mohamed Sidibe from National Bank.
Mohamed Sidibe: Maybe my first question, I can start with Diamba Sud and the positive resource update that you provided this morning. How should we think about the upcoming technical report? Will the increased resource be geared towards extending the mine life there? Or should we think about an improvement of the production profile in the first 2 to 5 years with maybe a little bit tonnage than previously expected. Any color would be great there.
Jorge Durant: Yes. No, we do not anticipate this will lead to a change in throughput against what we presented in the PEA, which was released in October. So this will, I believe, have 2 impacts this new update Mohamed, one will lead to an extension of life of mine, right? And second, the new resources coming in come at a higher grade. So the new deposit in the inventory is Southern Arc, which today is the largest deposit at the Diamba Sud camp. And it is also the highest grade one. So at 1.9 grams, I do would expect that annual production -- the annual production profile benefits to some degree from that uplift as well.
Mohamed Sidibe: That's clear on that front. And then so I guess a little bit more high grade in the front and then the lower grade material from the other assets can be used to extend the mine life there. If I can maybe ask yourself or David, maybe on the gold price assumption. So Diamba, you took it from about $2,600 to $3,300 per ounce. What was -- what are the key drivers behind that assumption? And if you can walk us through any reasoning behind that, using that price for the resource, please?
Jorge Durant: Yes. That is the resource that we have used. Right now, everybody is adjusting their price decks and we are using the methodology we use, the number we derived is $3,300 for the resource. So you should anticipate that for the reserve estimate, we use a lower gold price. Just as a reference, for our budgets and reserves for 2026, it's something we estimate with a cutoff date of -- in the second half of the year. And we use $2,600 gold for the resources and $2,300 gold for the reserve. So you should anticipate we use for reserves a lower number, a lower gold price compared to the 3,300 in the resource.
Mohamed Sidibe: That's great. And then maybe my final question on just the broader portfolio. I know you already guided to 2026, but how should we think about the cadence of production in the first half versus second half, specifically as with shipping at Seguela and production at Lindero? Just any color there would be appreciated.
Jorge Durant: Production through the year should be, in general, steady. The only one is Lindero, where production in Q1 should be -- Q1, Q2 should be expected to be a bit on the softer side as -- that's part of our plans. As Cesar described, we are engaged in improvements, changes to the foundations of the primary crusher and then gradually picking up a bit better in the second half of the year once all of those works are complete. Where do -- we do see an more variation is in AISC through the year.
We do expect a bit of a higher AISC in the beginning of the year, smoothing out, lowering throughout midyear into the second half to be where we guided, right? And that is just a function of capital expenditures being a bit more heavier in the first half of the year compared to the second half.
Operator: [Operator Instructions] Your next question is coming from John Pereira.
John Pereira: Sorry, I -- my line got disconnect. I'm not sure if there's any duplication from the previous caller. My questions are -- 1 of my questions is similar and really in terms of -- you talk about your plan to get to 500,000 ounces. And I'm just wondering if we could hear a little bit more color around that when you look at Seguela at current running rate of, we'll say, 160,000 ounces annually, if you can indeed achieve a 40% increase through your studies, that takes you to 225,000. And then obviously, Diamba Sud, if that goes forward, would contribute.
So I'd just like to understand a little bit more color on from the various projects, how you equate to 500,000 when you expect or how does that ramp over '26, '27 and '28? Answer whatever you can. I know I'm asking a lot here. And then in terms of cost for the various projects for example, in Seguela, if we want to move that from 160 to 225, do you have a sense of what the CapEx cost would be for that? Diamba Sud talked about in terms of previous news releases and in terms of capital costs.
But can you just give a little bit more flavor and then maybe if there's any increase in production expected from Lindero as well?
Jorge Durant: Yes, absolutely. Let's start with Seguela. Seguela is a mine that was originally designed to operate at a throughput rate of 1.25 million tonnes per year. That was the nameplate capacity of what we built and commissioned in mid-2023. Today, the mine is operating. For 2026, we have budgeted and guided for 1,750,000 ounces of throughput in the year, right? Our aim is to take it to 2.2 million, 2.3 million tons per year. That is a brownfields expansion of the processing plant. We're well advanced with the studies, and we have confidence right now that technically, it's a very straightforward project.
Most of the work will reside on the wet portion of the circuit, be it that thinners, pumping capacity, leach tanks. And we will certainly have to add a regrind ball mill. But as we understand it today, very little work will likely take place on the combination. So I can give you a broad range of the figure, we believe, will be required to materialize this expansion right now as the study is not complete, but the order of magnitude is in the range of probably $50 million, $60 million to $100 million on the high end. And by midyear, we will have a trade-off between the different options that we have and certainly final numbers for that.
But in terms of order of magnitude, those are the magnitude we're talking about, right? In -- but of course, the processing capacity is just a portion of this project because the foundation for this resides in the resource and in the reserve. And we just published a few weeks ago, an updated reserve and resource estimate for this mine. And what we're showing is that we have 1.5 million ounces of gold in reserves and 400,000 ounces in the indicated category and 700,000 ounces in the inferred. And we continue drilling and finding more. So you should expect that before midyear, probably April, May, we will be updating again the resources and reserves for this mine.
And it will be a constant deterioration for the next foreseeable future because we are having -- enjoying a lot of success with our drilling. So that is the foundation really for the expansion. And we are targeting 2.2 million tonnes per year, 2.3 million in that range. That range still needs to be well defined in the study. And that, with the grades we have in the reserve and in the resources that we do our modeling, should lead to a production in the range of 200,000 ounces of gold annually. So that is our target based on the work we're delivering. When can we achieve this?
If we have a study completed by mid-2026, I think a project of this nature, advancing it at a fast pace, we're not subject to any financial limitations on this one, we can advance it quickly and expectation would be that 12 to 18 months, I think, would be -- probably the limiting factor is delivery times on key equipment, for example, a rig or a mill, right? Right now, delivery times are around 12 months. So 12 to 18 months, I believe, is what should be expected from the gold decision. We might a long way decide to derisk the time line, advancing with some early purchases. That's something that we can consider. But we are not there yet.
We're still in the study phase. Moving on to the Diamba Sud, the same. Diamba Sud has a robust rich resource. We just updated it. We are very confident on the technical viability and economics of this project. We have a very strong PEA published in October that using $2,750 gold yields, an internal rate of return of 72% for our investment. So -- and that was with a smaller resource. So now with the figures we just updated, those -- this new resource, 1.25 million ounces indicated are going to inform the feasibility study that we aim to publish in May, June.
But we are confident and the best use of our funds right now is advance the project in a way that we derisk the time line for first gold. So we have decided to commit this year $100 million for the Diamba Sud project and $67 million of that $100 million figure are allocated for early works. What does that entail? We're building the camp. We are initiating excavations. We plan to initiate excavations on the water storage facility and other ancillary infrastructure. We are planning to purchase -- place early purchase orders for critical equipment packages, power generators, SAG mill and other equipment packages.
Placing those early orders will not only help secure our budget through the construction but also safeguard or time line to first gold. Everybody is happy right now about $4,000, $5,000 gold, but no one is thinking that everybody now wants to build a gold mine and the delivery times on the critical equipment that we use, the consumables or mines require, the people needed to execute all of these are quickly going to come in high demand and shortage, right? So how are we mitigating that risk?
Putting our capital to work and advancing as much as we can, placing early -- getting ourselves early in the queues for critical equipment, securing the best people and the best teams from the engineering firm. So we're doing a lot of that right now.
John Pereira: What do you consider long life? So you took a long life mine. You talked about 8 to 10 years is what you may be comfortable with?
Jorge Durant: The target for us is a decade. We need to see not solely on reserves, but also considering at least our resources, we need to see a decade, a decade plus. Yes.
John Pereira: So that tells me that we say within the next 2 or 3 years, you want to ramp to 500,000, 0.5 million ounces per year, then you are obviously in aggregate, going to target a resource of close to 5 million ounces through the various projects. So I guess you're well underway, certainly with Seguela, right? And Diamba Sud at 1.5 million [ ounces ] already, right?
Jorge Durant: Let me help you there. if I do something in -- currently today in our aggregate or consolidated reserves, if you look at our website, what you will see is that we have 3 million ounces in reserves today on a consolidated basis, 2.2 million ounces in indicated resources, which are of good quality and it's just a function of timing until we start converting a big chunk of that into the reserve. And we have 2 million ounces of gold in inferred categories, plus $50 million in drilling being spent this year in exploration, not just drilling, but exploration.
So the aggregate number, if I aggregate, which the regulators don't like, but if I -- just for the sake of conversation, the aggregate is over 7 million ounces. So we feel comfortable we have the resource base and reserve base to achieve our ambition.
John Pereira: Right. Do you still have anything -- any exploration going on in Mexico?
Jorge Durant: Yes. We do have some early stage exploration at 2 projects. One is being currently drilled. We don't talk much about those because those are early stage exploration. But yes, we still do some work. It's not a significant portion of the overall budget, but we're still there.
John Pereira: Okay. Great. And then just lastly on Lindero. Where do you see that the production for Lindero going? Is there any growth or expansion plans planned for Lindero?
Jorge Durant: Today, Lindero enjoys a decade in reserves, right? Reserves and resources, we clearly have a -- we're comfortable with 19 years there, right now as it sits. And Cesar touched on this during his intervention. We currently have a drill program because at the pit -- at the bottom of -- below the bottom of the pit, we have a open mineralization and we are targeting -- this is a target of 400,000 ounces of gold that we're currently drilling at the bottom of the pit. How much of that are we going to capture? Let me get back to you once the drilling is complete, but that is the target.
And we're drilling -- we're set to start drilling in March, I believe, and so before year -- midyear, that program should be completed, and I expect we'll see a big portion of those ounces coming into the inventory mid in the second half of the year. Our budget there for exploration is about $5 million this year. Yes.
Operator: Your next question is coming from Mohamed Sidibe from National Bank.
Mohamed Sidibe: Just Seguela, maybe as you relate to the underground, could you share some color on when -- about the underground development plans you have there for Sunbird and when we could start to see ore from the underground within your plan? I'm not sure if you can give any color on that front.
Jorge Durant: Yes. We have, Mohamed, a budget this year of around $14 million that will likely grow some. This year, we want to start the box cut and some purchases of underground equipment. The idea is that we are doing excavations in 2027, so probably late 2027, early 2028 is when we can start seeing production. Remember that we're still permitting. We're still permitting underground. So we expect we can achieve our permits late this year. I was at Indaba with the team, David and the team, we had a good meeting with the Director of Mines.
For Sene -- Ivory Coast, and he was very keen to advance with the permitting and with the aim of having it permitted this year. So if we take his word, if we're permitted this year, we can initiate mining next, right? This will require ramps and crosscuts and ancillary infrastructure that will likely be developed throughout 2027 and first production in 2028.
Operator: [Operator Instructions] That concludes our Q&A session. I will now hand the conference back to Carlos Baca, Vice President of Investor Relations, for closing remarks. Please go ahead.
Carlos Baca: Thank you, Matthew. If there are no further questions, I'd like to thank everyone for joining us today. We appreciate your continued support and interest in Fortuna Mining. Have a great day.
Operator: Thank you, everyone. This concludes today's event. You may disconnect at this time, and have a wonderful day. Thank you for your participation.
Before you buy stock in Fortuna Mining, consider this:
The Motley Fool Stock Advisor analyst team just identified what they believe are the 10 best stocks for investors to buy now… and Fortuna Mining wasn’t one of them. The 10 stocks that made the cut could produce monster returns in the coming years.
Consider when Netflix made this list on December 17, 2004... if you invested $1,000 at the time of our recommendation, you’d have $420,595!* Or when Nvidia made this list on April 15, 2005... if you invested $1,000 at the time of our recommendation, you’d have $1,152,356!*
Now, it’s worth noting Stock Advisor’s total average return is 899% — a market-crushing outperformance compared to 194% for the S&P 500. Don't miss the latest top 10 list, available with Stock Advisor, and join an investing community built by individual investors for individual investors.
See the 10 stocks »
*Stock Advisor returns as of February 19, 2026.
This article is a transcript of this conference call produced for The Motley Fool. While we strive for our Foolish Best, there may be errors, omissions, or inaccuracies in this transcript. Parts of this article were created using Large Language Models (LLMs) based on The Motley Fool's insights and investing approach. It has been reviewed by our AI quality control systems. Since LLMs cannot (currently) own stocks, it has no positions in any of the stocks mentioned. As with all our articles, The Motley Fool does not assume any responsibility for your use of this content, and we strongly encourage you to do your own research, including listening to the call yourself and reading the company's SEC filings. Please see our Terms and Conditions for additional details, including our Obligatory Capitalized Disclaimers of Liability.
The Motley Fool has no position in any of the stocks mentioned. The Motley Fool has a disclosure policy.